| Assessment Year | 1991 |
|---|---|
| Principal Product | TEFLON TUBINGS |
| NAICS |
n/a
|
| SIC | 3052: Rubber and Plastics Hose and Belting |
| Sales Range | $10 M to 50M |
| # of Employees | 100 |
| Plant Area |
n/a
|
| Annual Production | 7,000
thousand feet
|
| Production Hrs. Annual | 7,488
hrs
|
| Location (State) | New Jersey |
Facility Energy Cost and Usage
| Source | Yearly Cost | Usage | Unit Cost | |
|---|---|---|---|---|
| Electricity Usage | $165,772 | 2,003,517 |
kWh
|
$0.083 |
| Natural Gas | $57,400 | 11,042 |
MMBtu
|
$5.20 |
| TOTAL YEARLY COSTS | - | |||
| RECOMMENDED SAVINGS* | $39,024 |
See individual recommendations below
*Non-energy impacts included in savings.
|
||
| IMPLEMENTED SAVINGS* | $39,024 | |||
Recommendations
| # | Description | Yearly Savings* | Imp'd Cost* | Status | Electricity Usage Savings | Natural Gas Savings |
|---|---|---|---|---|---|---|
| 01 | 2.2522: Isolate hot or cold equipment | $2,985 | $1,200 |
$2,985
36,049
kWh
|
- | |
| 02 | 2.2522: Isolate hot or cold equipment | $1,965 | $450 |
$1,965
23,740
kWh
|
- | |
| 03 | 2.6212: Turn off equipment during breaks, reduce operating time | $28,708 | - | - |
$28,708
-
MMBtu
|
|
| 04 | 2.7142: Utilize higher efficiency lamps and/or ballasts | $5,366 | $830 |
$5,366
64,771
kWh
|
- | |
| TOTAL RECOMMENDED | $39,024 | $2,480 |
$10,316
124,560
kWh
|
$28,708
-
MMBtu
|
||
| TOTAL IMPLEMENTED | $39,024 | $2,480 |
$10,316
124,560
kWh
|
$28,708
-
MMBtu
|
||
*Savings and costs are best estimates based on the center's site visit, associated engineering analysis, and typical capital and labor costs