ITAC Assessment: UF0169
ITAC logo
ITAC Assessment: UF0169
Grant Funding Opportunity NOW OPEN
Up to $300k at 50% cost share for qualifying* projects.
Grant Funding Opportunity Open
Qualifying* small and medium-sized US manufacturers, that received an ITAC, Onsite Energy/CHP TAP, or qualified equivalent assessment since 2018 can now apply for grants for implementation of assessment recommendations at up to 50% of qualifying* project costs with a maximum of $300,000 per grant.
IMPORTANT: The grant program now operates on a rolling basis and applications may be submitted at any time through the year, with quarterly reviews.
*See Full Grant Solicitation for full qualification and selection details.
Assessment Year 1997
Principal Product Mobile Homes
NAICS
n/a
SIC 2451: Mobile Homes
Sales Range $10
M
to 50
M
# of Employees 150
Plant Area 70,000
ft2
Annual Production 1,979
pieces
Production Hrs. Annual 3,300
hrs
Location (State) Florida

Facility Energy Cost and Usage

Source Yearly Cost Usage
Electricity Usage $49,006 965,416
kWh
Electricity Demand $33,452 3,914
kW-mo/yr
TOTAL YEARLY COSTS -
RECOMMENDED SAVINGS* $141,299 *Non-energy impacts included in savings.
IMPLEMENTED SAVINGS* $99,012

Recommendations

# Description Yearly Savings* Imp'd Cost* Status Electricity Usage Savings Electricity Demand Savings Solid Waste (non-haz) Savings Administrative Changes Savings Primary Raw Material Savings Ancillary Material Cost Savings By-product Production Savings
01 2.4133: Use most efficient type of electric motors $1,231 $555 $1,057
5,275
kWh
$174
-
kW-mo/yr
- - - - -
02 2.7232: Replace existing hvac unit with high efficiency model $1,538 $333 $1,372
5,275
kWh
$166
-
kW-mo/yr
- - - - -
03 2.4236: Eliminate leaks in inert gas and compressed air lines/ valves $8,439 $1,850 $8,439
165,592
kWh
- - - - - -
04 2.4226: Use / purchase optimum sized compressor $5,674 $1,500 - $5,674
-
kW-mo/yr
- - - - -
05 3.5315: Lease / purchase baler; sell cardboard to recycler $10,810 $18,400 - - $6,600
-
lb
- - - $4,210
06 3.6193: Install equipment (eg compactor) to reduce disposal costs $25,073 $5,500 $(-262.0)
(-4,982)
kWh
- - $(-9,945.0) - $35,280 -
07 3.1191: Change procedures / equipment / operating conditions $3,125 $25 - - - - $3,125 - -
08 4.425: Eliminate/reduce redundant inspections $8,415 - - - - $8,415 - - -
09 4.431: Train operators for maximum operating efficiency $20,994 $3,120 - - - $13,600 - $7,394 -
10 4.421: Modify current incentive program $56,000 $50,000 - - - $56,000 - - -
TOTAL RECOMMENDED $141,299 $81,283 $10,606
171,160
kWh
$6,014
-
kW-mo/yr
$6,600
-
lb
$68,070 $3,125 $42,674 $4,210
TOTAL IMPLEMENTED $99,012 $74,258 $10,868
176,142
kWh
$340
-
kW-mo/yr
$6,600
-
lb
$69,600 - $7,394 $4,210
Yearly Savings* Imp'd Cost* Electricity Usage Savings Electricity Demand Savings Solid Waste (non-haz) Savings Administrative Changes Savings Primary Raw Material Savings Ancillary Material Cost Savings By-product Production Savings
*Savings and costs are best estimates based on the center's site visit, associated engineering analysis, and typical capital and labor costs