| Assessment Year | 1997 |
|---|---|
| Principal Product | Mobile Homes |
| NAICS |
n/a
|
| SIC | 2451: Mobile Homes |
| Sales Range | $10 M to 50M |
| # of Employees | 150 |
| Plant Area |
70,000
ft2
|
| Annual Production | 1,979
pieces
|
| Production Hrs. Annual | 3,300
hrs
|
| Location (State) | Florida |
Facility Energy Cost and Usage
| Source | Yearly Cost | Usage | Unit Cost | |
|---|---|---|---|---|
| Electricity Usage | $49,006 | 965,416 |
kWh
|
$0.051 |
| Electricity Demand | $33,452 | 3,914 |
kW-mo/yr
|
$8.55 |
| TOTAL YEARLY COSTS | - | |||
| RECOMMENDED SAVINGS* | $141,299 |
See individual recommendations below
*Non-energy impacts included in savings.
|
||
| IMPLEMENTED SAVINGS* | $99,012 | |||
Recommendations
| # | Description | Yearly Savings* | Imp'd Cost* | Status | Electricity Usage Savings | Electricity Demand Savings | Solid Waste (non-haz) Savings | Administrative Changes Savings | Primary Raw Material Savings | Ancillary Material Cost Savings | By-product Production Savings |
|---|---|---|---|---|---|---|---|---|---|---|---|
| 01 | 2.4133: Use most efficient type of electric motors | $1,231 | $555 |
$1,057
5,275
kWh
|
$174
-
kW-mo/yr
|
- | - | - | - | - | |
| 02 | 2.7232: Replace existing hvac unit with high efficiency model | $1,538 | $333 |
$1,372
5,275
kWh
|
$166
-
kW-mo/yr
|
- | - | - | - | - | |
| 03 | 2.4236: Eliminate leaks in inert gas and compressed air lines/ valves | $8,439 | $1,850 |
$8,439
165,592
kWh
|
- | - | - | - | - | - | |
| 04 | 2.4226: Use / purchase optimum sized compressor | $5,674 | $1,500 | - |
$5,674
-
kW-mo/yr
|
- | - | - | - | - | |
| 05 | 3.5315: Lease / purchase baler; sell cardboard to recycler | $10,810 | $18,400 | - | - |
$6,600
-
lb
|
- | - | - | $4,210 | |
| 06 | 3.6193: Install equipment (eg compactor) to reduce disposal costs | $25,073 | $5,500 |
$(-262.0)
(-4,982)
kWh
|
- | - | $(-9,945.0) | - | $35,280 | - | |
| 07 | 3.1191: Change procedures / equipment / operating conditions | $3,125 | $25 | - | - | - | - | $3,125 | - | - | |
| 08 | 4.425: Eliminate/reduce redundant inspections | $8,415 | - | - | - | - | $8,415 | - | - | - | |
| 09 | 4.431: Train operators for maximum operating efficiency | $20,994 | $3,120 | - | - | - | $13,600 | - | $7,394 | - | |
| 10 | 4.421: Modify current incentive program | $56,000 | $50,000 | - | - | - | $56,000 | - | - | - | |
| TOTAL RECOMMENDED | $141,299 | $81,283 |
$10,606
171,160
kWh
|
$6,014
-
kW-mo/yr
|
$6,600
-
lb
|
$68,070 | $3,125 | $42,674 | $4,210 | ||
| TOTAL IMPLEMENTED | $99,012 | $74,258 |
$10,868
176,142
kWh
|
$340
-
kW-mo/yr
|
$6,600
-
lb
|
$69,600 | - | $7,394 | $4,210 | ||
| Yearly Savings* | Imp'd Cost* | Electricity Usage Savings | Electricity Demand Savings | Solid Waste (non-haz) Savings | Administrative Changes Savings | Primary Raw Material Savings | Ancillary Material Cost Savings | By-product Production Savings | |||
*Savings and costs are best estimates based on the center's site visit, associated engineering analysis, and typical capital and labor costs