Assessment Year | 1997 |
---|---|
Principal Product | Frozen Food |
NAICS |
n/a
|
SIC | 2091: Canned and Cured Fish and Seafoods |
Sales Range | $10 M to 50M |
# of Employees | 100 |
Plant Area |
60,000
ft2
|
Annual Production | 300,000
pieces
|
Production Hrs. Annual | 2,210
hrs
|
Location (State) | Florida |
Facility Energy Cost and Usage
Source | Yearly Cost | Usage | Unit Cost | |
---|---|---|---|---|
Electricity Usage | $121,282 | 3,577,667 |
kWh
|
$0.034 |
Electricity Demand | $95,784 | 8,020 |
kW-mo/yr
|
$11.94 |
Natural Gas | $10,294 | 13,770 |
MMBtu
|
$0.75 |
TOTAL YEARLY COSTS | - | |||
RECOMMENDED SAVINGS* | $531,525 |
See individual recommendations below
*Non-energy impacts included in savings.
|
||
IMPLEMENTED SAVINGS* | $18,075 |
Recommendations
# | Description | Yearly Savings* | Imp'd Cost* | Status | Electricity Usage Savings | Electricity Demand Savings | Natural Gas Savings | Solid Waste (non-haz) Savings | Administrative Changes Savings | Primary Raw Material Savings |
---|---|---|---|---|---|---|---|---|---|---|
01 | 2.7142: Utilize higher efficiency lamps and/or ballasts | $7,489 | $20,613 |
$3,705
109,027
kWh
|
$3,784
-
kW-mo/yr
|
- | - | - | - | |
02 | 2.4133: Use most efficient type of electric motors | $414 | $426 |
$246
7,327
kWh
|
$168
-
kW-mo/yr
|
- | - | - | - | |
03 | 2.4239: Eliminate or reduce compressed air usage | $3,842 | $8,000 |
$1,372
40,445
kWh
|
$2,470
-
kW-mo/yr
|
- | - | - | - | |
04 | 2.4236: Eliminate leaks in inert gas and compressed air lines/ valves | $2,062 | $1,350 |
$2,062
33,705
kWh
|
- | - | - | - | - | |
05 | 2.2437: Recover waste heat from equipment | $3,369 | $750 | - | - |
$3,369
-
MMBtu
|
- | - | - | |
06 | 2.2615: Clean condenser tubes | $5,814 | - |
$5,814
228,019
kWh
|
- | - | - | - | - | |
07 | 4.231: Purchase equipment instead of leasing | $482,839 | $1,600,000 | - | - | - | - | $482,839 | - | |
08 | 3.5315: Lease / purchase baler; sell cardboard to recycler | $2,296 | $7,000 | - | - | - |
$2,296
-
lb
|
- | - | |
09 | 3.1191: Change procedures / equipment / operating conditions | $23,400 | - | - | - | - | - | - | $23,400 | |
TOTAL RECOMMENDED | $531,525 | $1,638,139 |
$13,199
418,523
kWh
|
$6,422
-
kW-mo/yr
|
$3,369
-
MMBtu
|
$2,296
-
lb
|
$482,839 | $23,400 | ||
TOTAL IMPLEMENTED | $18,075 | $29,389 |
$11,827
378,078
kWh
|
$3,952
-
kW-mo/yr
|
- |
$2,296
-
lb
|
- | - | ||
Yearly Savings* | Imp'd Cost* | Electricity Usage Savings | Electricity Demand Savings | Natural Gas Savings | Solid Waste (non-haz) Savings | Administrative Changes Savings | Primary Raw Material Savings |
*Savings and costs are best estimates based on the center's site visit, associated engineering analysis, and typical capital and labor costs