ITAC Assessment: UF0137
ITAC logo
ITAC Assessment: UF0137
Grant Funding Opportunity NOW OPEN
Up to $300k at 50% cost share for qualifying* projects.
Grant Funding Opportunity Open
Qualifying* small and medium-sized US manufacturers, that received an ITAC, Onsite Energy/CHP TAP, or qualified equivalent assessment since 2018 can now apply for grants for implementation of assessment recommendations at up to 50% of qualifying* project costs with a maximum of $300,000 per grant.
IMPORTANT: The grant program now operates on a rolling basis and applications may be submitted at any time through the year, with quarterly reviews.
*See Full Grant Solicitation for full qualification and selection details.
Assessment Year 1996
Principal Product Intraocular lens
NAICS
n/a
SIC 3851: Ophthalmic Goods
Sales Range $50
M
to 100
M
# of Employees 190
Plant Area 100,000
ft2
Annual Production 400,000
pieces
Production Hrs. Annual 3,640
hrs
Location (State) Florida

Facility Energy Cost and Usage

Source Yearly Cost Usage
Electricity Usage $383,839 6,401,817
kWh
Electricity Demand $52,580 11,840
kW-mo/yr
TOTAL YEARLY COSTS -
RECOMMENDED SAVINGS* $86,728 *Non-energy impacts included in savings.
IMPLEMENTED SAVINGS* $36,208

Recommendations

# Description Yearly Savings* Imp'd Cost* Status Electricity Usage Savings Administrative Changes Savings Ancillary Material Cost Savings Water Consumption Savings
01 2.6231: Utilize controls to operate equipment only when needed $21,085 $5,000 $21,085
405,334
kWh
- - -
02 2.4236: Eliminate leaks in inert gas and compressed air lines/ valves $3,664 $350 $3,664
60,961
kWh
- - -
03 2.4146: Use adjustable frequency drive or multiple speed motors on existing system $25,358 $34,340 $25,358
487,691
kWh
- - -
04 2.2437: Recover waste heat from equipment $9,176 $14,000 $9,176
176,436
kWh
- - -
05 3.6192: Use a less expensive method of waste removal $600 - - $600 - -
06 3.1191: Change procedures / equipment / operating conditions $21,580 - - - $21,580 -
07 3.4151: Minimize water usage $3,477 $3,400 - - - $3,477
-
Tgal
08 3.4155: Meter waste water $1,788 $2,000 - $1,788 - -
TOTAL RECOMMENDED $86,728 $59,090 $59,283
1,130,422
kWh
$2,388 $21,580 $3,477
-
Tgal
TOTAL IMPLEMENTED $36,208 $16,350 $12,840
237,397
kWh
$1,788 $21,580 -
Yearly Savings* Imp'd Cost* Electricity Usage Savings Administrative Changes Savings Ancillary Material Cost Savings Water Consumption Savings
*Savings and costs are best estimates based on the center's site visit, associated engineering analysis, and typical capital and labor costs