ITAC Assessment: MZ0300
ITAC logo
ITAC Assessment: MZ0300
Grant Funding Opportunity NOW OPEN
Up to $300k at 50% cost share for qualifying* projects.
Grant Funding Opportunity Open
Qualifying* small and medium-sized US manufacturers, that received an ITAC, Onsite Energy/CHP TAP, or qualified equivalent assessment since 2018 can now apply for grants for implementation of assessment recommendations at up to 50% of qualifying* project costs with a maximum of $300,000 per grant.
IMPORTANT: The grant program now operates on a rolling basis and applications may be submitted at any time through the year, with quarterly reviews.
*See Full Grant Solicitation for full qualification and selection details.
Assessment Year 2020
Principal Product Remanufactured engines and components
NAICS 333618: Other Engine Equipment Manufacturing
SIC 3519: Internal Combustion Engines, Not Elsewhere Classified
Sales Range $50
M
to 100
M
# of Employees 300
Plant Area 255,000
ft2
Annual Production 35,000
pieces
Production Hrs. Annual 4,160
hrs
Location (State) Missouri

Facility Energy Cost and Usage

Source Yearly Cost Usage
Electricity Usage $370,135 4,347,210
kWh
Natural Gas $79,987 14,820
MMBtu
Waste Disposal Costs
Water Usage $11,611 2,661
Tgal
Water Disposal $23,152 2,661
Tgal
TOTAL YEARLY COSTS $484,885
RECOMMENDED SAVINGS* $30,223 *Non-energy impacts included in savings.
IMPLEMENTED SAVINGS* $5,382

Recommendations

# Description Yearly Savings* Imp'd Cost* Status Electricity Usage Savings Water Disposal Savings One-time Revenue or Avoided Cost Savings
01 2.7142: Utilize higher efficiency lamps and/or ballasts $2,598 $1,650 $1,977
23,253
kWh
- $621
02 2.7135: Install occupancy sensors $783 $460 $783
9,216
kWh
- -
03 2.7447: Install vinyl strip / high speed / air curtain doors $1,074 $5,200 $1,074
12,635
kWh
- -
04 2.4231: Reduce the pressure of compressed air to the minimum required $5,728 $4,770 $5,728
67,390
kWh
- -
05 2.4239: Eliminate or reduce compressed air usage $5,678 $3,310 $5,678
66,791
kWh
- -
06 2.4236: Eliminate leaks in inert gas and compressed air lines/ valves $2,784 $200 $2,784
32,755
kWh
- -
07 3.4116: Meter recycled water (to reduce sewer charges) $11,578 $3,168 - $11,578
-
Tgal
-
TOTAL RECOMMENDED $30,223 $18,758 $18,024
212,040
kWh
$11,578
-
Tgal
$621
TOTAL IMPLEMENTED $5,382 $1,850 $4,761
56,008
kWh
- $621
Yearly Savings* Imp'd Cost* Electricity Usage Savings Water Disposal Savings One-time Revenue or Avoided Cost Savings
*Savings and costs are best estimates based on the center's site visit, associated engineering analysis, and typical capital and labor costs