ITAC Assessment: UF0115
ITAC logo
ITAC Assessment: UF0115
Grant Funding Opportunity NOW OPEN
Up to $300k at 50% cost share for qualifying* projects.
Grant Funding Opportunity Open
Qualifying* small and medium-sized US manufacturers, that received an ITAC, Onsite Energy/CHP TAP, or qualified equivalent assessment since 2018 can now apply for grants for implementation of assessment recommendations at up to 50% of qualifying* project costs with a maximum of $300,000 per grant.
IMPORTANT: The grant program now operates on a rolling basis and applications may be submitted at any time through the year, with quarterly reviews.
*See Full Grant Solicitation for full qualification and selection details.
Assessment Year 1995
Principal Product Pneumatic Cylinders
NAICS
n/a
SIC 3492: Fluid Power Valves and Hose Fittings
Sales Range $10
M
to 50
M
# of Employees 120
Plant Area 20,000
ft2
Annual Production 140,000
pieces
Production Hrs. Annual 2,100
hrs
Location (State) Florida

Facility Energy Cost and Usage

Source Yearly Cost Usage
Electricity Usage $59,386 638,628
kWh
TOTAL YEARLY COSTS -
RECOMMENDED SAVINGS* $8,581 *Non-energy impacts included in savings.
IMPLEMENTED SAVINGS* $4,268

Recommendations

# Description Yearly Savings* Imp'd Cost* Status Electricity Usage Savings
01 2.7142: Utilize higher efficiency lamps and/or ballasts $2,197 $919 $2,197
25,205
kWh
02 2.7232: Replace existing hvac unit with high efficiency model $2,494 $4,500 $2,494
25,205
kWh
03 2.6231: Utilize controls to operate equipment only when needed $1,819 $1,500 $1,819
28,429
kWh
04 2.4133: Use most efficient type of electric motors $420 $1,364 $420
4,396
kWh
05 2.4111: Utilize energy-efficient belts and other improved mechanisms $111 $183 $111
1,758
kWh
06 2.4236: Eliminate leaks in inert gas and compressed air lines/ valves $1,540 $500 $1,540
16,706
kWh
TOTAL RECOMMENDED $8,581 $8,966 $8,581
101,699
kWh
TOTAL IMPLEMENTED $4,268 $2,966 $4,268
48,065
kWh
Yearly Savings* Imp'd Cost* Electricity Usage Savings
*Savings and costs are best estimates based on the center's site visit, associated engineering analysis, and typical capital and labor costs