ITAC Assessment: GT0491
ITAC logo
ITAC Assessment: GT0491
Grant Funding Opportunity NOW OPEN
Up to $300k at 50% cost share for qualifying* projects.
Grant Funding Opportunity Open
Qualifying* small and medium-sized US manufacturers, that received an ITAC, Onsite Energy/CHP TAP, or qualified equivalent assessment since 2018 can now apply for grants for implementation of assessment recommendations at up to 50% of qualifying* project costs with a maximum of $300,000 per grant.
IMPORTANT: The grant program now operates on a rolling basis and applications may be submitted at any time through the year, with quarterly reviews.
*See Full Grant Solicitation for full qualification and selection details.
Assessment Year 1993
Principal Product Flexible Packaging
NAICS
n/a
SIC 2679: Converted Paper and Paperboard Products, Not Elsewhere Classified
Sales Range $50
M
to 100
M
# of Employees 355
Plant Area 140,000
ft2
Annual Production 80,000,000
thousand feet
Production Hrs. Annual 7,344
hrs
Location (State) Georgia

Facility Energy Cost and Usage

Source Yearly Cost Usage
Electricity Usage $648,319 12,616,647
kWh
Natural Gas $134,925 46,223
MMBtu
TOTAL YEARLY COSTS -
RECOMMENDED SAVINGS* $66,400 *Non-energy impacts included in savings.
IMPLEMENTED SAVINGS* $47,425

Recommendations

# Description Yearly Savings* Imp'd Cost* Status Electricity Usage Savings
01 2.7142: Utilize higher efficiency lamps and/or ballasts $500 $1,000 $500
9,672
kWh
02 2.7142: Utilize higher efficiency lamps and/or ballasts $680 $1,470 $680
13,189
kWh
03 2.7142: Utilize higher efficiency lamps and/or ballasts $19,260 $57,715 $19,260
374,853
kWh
04 2.7135: Install occupancy sensors $2,600 $1,550 $2,600
49,824
kWh
05 2.4111: Utilize energy-efficient belts and other improved mechanisms $3,970 - $3,970
77,081
kWh
06 2.4221: Install compressor air intakes in coolest locations $345 $450 $345
6,741
kWh
07 2.7124: Make a practice of turning off lights when not needed $3,795 - $3,795
73,857
kWh
08 2.6218: Turn off equipment when not in use $5,540 $4,000 $5,540
107,855
kWh
09 2.5194: Redesign process $5,340 $5,840 $5,340
104,338
kWh
10 2.5194: Redesign process $24,370 $42,000 $24,370
311,841
kWh
TOTAL RECOMMENDED $66,400 $114,025 $66,400
1,129,251
kWh
TOTAL IMPLEMENTED $47,425 $99,715 $47,425
760,551
kWh
Yearly Savings* Imp'd Cost* Electricity Usage Savings
*Savings and costs are best estimates based on the center's site visit, associated engineering analysis, and typical capital and labor costs