Assessment Year | 1993 |
---|---|
Principal Product | Flexible Packaging |
NAICS |
n/a
|
SIC | 2679: Converted Paper and Paperboard Products, Not Elsewhere Classified |
Sales Range | $50 M to 100M |
# of Employees | 355 |
Plant Area |
140,000
ft2
|
Annual Production | 80,000,000
thousand feet
|
Production Hrs. Annual | 7,344
hrs
|
Location (State) | Georgia |
Facility Energy Cost and Usage
Source | Yearly Cost | Usage | Unit Cost | |
---|---|---|---|---|
Electricity Usage | $648,319 | 12,616,647 |
kWh
|
$0.051 |
Natural Gas | $134,925 | 46,223 |
MMBtu
|
$2.92 |
TOTAL YEARLY COSTS | - | |||
RECOMMENDED SAVINGS* | $66,400 |
See individual recommendations below
*Non-energy impacts included in savings.
|
||
IMPLEMENTED SAVINGS* | $47,425 |
Recommendations
# | Description | Yearly Savings* | Imp'd Cost* | Status | Electricity Usage Savings |
---|---|---|---|---|---|
01 | 2.7142: Utilize higher efficiency lamps and/or ballasts | $500 | $1,000 |
$500
9,672
kWh
|
|
02 | 2.7142: Utilize higher efficiency lamps and/or ballasts | $680 | $1,470 |
$680
13,189
kWh
|
|
03 | 2.7142: Utilize higher efficiency lamps and/or ballasts | $19,260 | $57,715 |
$19,260
374,853
kWh
|
|
04 | 2.7135: Install occupancy sensors | $2,600 | $1,550 |
$2,600
49,824
kWh
|
|
05 | 2.4111: Utilize energy-efficient belts and other improved mechanisms | $3,970 | - |
$3,970
77,081
kWh
|
|
06 | 2.4221: Install compressor air intakes in coolest locations | $345 | $450 |
$345
6,741
kWh
|
|
07 | 2.7124: Make a practice of turning off lights when not needed | $3,795 | - |
$3,795
73,857
kWh
|
|
08 | 2.6218: Turn off equipment when not in use | $5,540 | $4,000 |
$5,540
107,855
kWh
|
|
09 | 2.5194: Redesign process | $5,340 | $5,840 |
$5,340
104,338
kWh
|
|
10 | 2.5194: Redesign process | $24,370 | $42,000 |
$24,370
311,841
kWh
|
|
TOTAL RECOMMENDED | $66,400 | $114,025 |
$66,400
1,129,251
kWh
|
||
TOTAL IMPLEMENTED | $47,425 | $99,715 |
$47,425
760,551
kWh
|
||
Yearly Savings* | Imp'd Cost* | Electricity Usage Savings |
*Savings and costs are best estimates based on the center's site visit, associated engineering analysis, and typical capital and labor costs