ITAC Assessment: UF0065
ITAC logo
ITAC Assessment: UF0065
Grant Funding Opportunity NOW OPEN
Up to $300k at 50% cost share for qualifying* projects.
Grant Funding Opportunity Open
Qualifying* small and medium-sized US manufacturers, that received an ITAC, Onsite Energy/CHP TAP, or qualified equivalent assessment since 2018 can now apply for grants for implementation of assessment recommendations at up to 50% of qualifying* project costs with a maximum of $300,000 per grant.
IMPORTANT: The grant program now operates on a rolling basis and applications may be submitted at any time through the year, with quarterly reviews.
*See Full Grant Solicitation for full qualification and selection details.
Assessment Year 1993
Principal Product Ducts and Pipes
NAICS
n/a
SIC 3444: Sheet Metal Work
Sales Range $10
M
to 50
M
# of Employees 150
Plant Area 96,000
ft2
Annual Production 12,000,000
pieces
Production Hrs. Annual 2,184
hrs
Location (State) Florida

Facility Energy Cost and Usage

Source Yearly Cost Usage
Electricity Usage $72,120 899,472
kWh
Natural Gas $2,014 285
MMBtu
TOTAL YEARLY COSTS -
RECOMMENDED SAVINGS* $10,148 *Non-energy impacts included in savings.
IMPLEMENTED SAVINGS* -

Recommendations

# Description Yearly Savings* Imp'd Cost* Status Electricity Usage Savings
01 2.7142: Utilize higher efficiency lamps and/or ballasts $3,008 $743 $3,008
37,515
kWh
02 2.7142: Utilize higher efficiency lamps and/or ballasts $835 $4,141 $835
10,551
kWh
03 2.4133: Use most efficient type of electric motors $2,219 $4,702 $2,219
27,843
kWh
04 2.4111: Utilize energy-efficient belts and other improved mechanisms $200 $800 $200
2,638
kWh
05 2.7232: Replace existing hvac unit with high efficiency model $1,871 $5,900 $1,871
23,447
kWh
06 2.6231: Utilize controls to operate equipment only when needed $2,015 $3,000 $2,015
25,205
kWh
TOTAL RECOMMENDED $10,148 $19,286 $10,148
127,199
kWh
TOTAL IMPLEMENTED - - -
Yearly Savings* Imp'd Cost* Electricity Usage Savings
*Savings and costs are best estimates based on the center's site visit, associated engineering analysis, and typical capital and labor costs