ITAC Assessment: UF0042
ITAC logo
ITAC Assessment: UF0042
Grant Funding Opportunity NOW OPEN
Up to $300k at 50% cost share for qualifying* projects.
Grant Funding Opportunity Open
Qualifying* small and medium-sized US manufacturers, that received an ITAC, Onsite Energy/CHP TAP, or qualified equivalent assessment since 2018 can now apply for grants for implementation of assessment recommendations at up to 50% of qualifying* project costs with a maximum of $300,000 per grant.
IMPORTANT: The grant program now operates on a rolling basis and applications may be submitted at any time through the year, with quarterly reviews.
*See Full Grant Solicitation for full qualification and selection details.
Assessment Year 1992
Principal Product STEEL WIRE AND CABLE
NAICS
n/a
SIC 3531: Construction Machinery and Equipment
Sales Range $10
M
to 50
M
# of Employees 180
Plant Area
n/a
Annual Production 36,000
ton
Production Hrs. Annual 7,488
hrs
Location (State) Florida

Facility Energy Cost and Usage

Source Yearly Cost Usage
Electricity Usage $866,463 12,917,351
kWh
Natural Gas $87,446 18,557
MMBtu
TOTAL YEARLY COSTS -
RECOMMENDED SAVINGS* $32,772 *Non-energy impacts included in savings.
IMPLEMENTED SAVINGS* -

Recommendations

# Description Yearly Savings* Imp'd Cost* Status Electricity Usage Savings
01 2.7142: Utilize higher efficiency lamps and/or ballasts $2,115 $304 $2,115
31,653
kWh
02 2.7144: Install spectral reflectors / delamp $8,070 $7,350 $8,070
120,164
kWh
03 2.7142: Utilize higher efficiency lamps and/or ballasts $449 $912 $449
6,741
kWh
04 2.6232: Install set-back timers $1,291 $1,200 $1,291
19,343
kWh
05 2.4133: Use most efficient type of electric motors $2,536 $10,873 $2,536
37,808
kWh
06 2.7233: Use properly designed and sized hvac equipment $537 $2,860 $537
7,913
kWh
07 2.3212: Optimize plant power factor $17,774 $16,180 $17,774
-
kWh
TOTAL RECOMMENDED $32,772 $39,679 $32,772
223,622
kWh
TOTAL IMPLEMENTED - - -
Yearly Savings* Imp'd Cost* Electricity Usage Savings
*Savings and costs are best estimates based on the center's site visit, associated engineering analysis, and typical capital and labor costs