| Assessment Year | 1992 |
|---|---|
| Principal Product | EMERGENCY VEHICLE CHASIS |
| NAICS |
n/a
|
| SIC | 3713: Truck and Bus Bodies |
| Sales Range | $10 M to 50M |
| # of Employees | 280 |
| Plant Area |
n/a
|
| Annual Production | 800
pieces
|
| Production Hrs. Annual | 4,420
hrs
|
| Location (State) | Florida |
Facility Energy Cost and Usage
| Source | Yearly Cost | Usage | Unit Cost | |
|---|---|---|---|---|
| Electricity Usage | $120,477 | 1,751,759 |
kWh
|
$0.069 |
| Natural Gas | $10,871 | 2,200 |
MMBtu
|
$4.94 |
| TOTAL YEARLY COSTS | - | |||
| RECOMMENDED SAVINGS* | $42,918 |
See individual recommendations below
*Non-energy impacts included in savings.
|
||
| IMPLEMENTED SAVINGS* | $6,204 | |||
Recommendations
| # | Description | Yearly Savings* | Imp'd Cost* | Status | Electricity Usage Savings |
|---|---|---|---|---|---|
| 01 | 2.7142: Utilize higher efficiency lamps and/or ballasts | $2,249 | $1,872 |
$2,249
32,532
kWh
|
|
| 02 | 2.7111: Reduce illumination to minimum necessary levels | $10,336 | $40,290 |
$10,336
149,766
kWh
|
|
| 03 | 2.7142: Utilize higher efficiency lamps and/or ballasts | $2,183 | $6,024 |
$2,183
31,653
kWh
|
|
| 04 | 2.6232: Install set-back timers | $1,347 | $1,200 |
$1,347
19,637
kWh
|
|
| 05 | 2.7233: Use properly designed and sized hvac equipment | $2,402 | $1,980 |
$2,402
34,877
kWh
|
|
| 06 | 2.4133: Use most efficient type of electric motors | $431 | $4,943 |
$431
6,155
kWh
|
|
| 07 | 2.4111: Utilize energy-efficient belts and other improved mechanisms | $659 | $575 |
$659
9,672
kWh
|
|
| 08 | 2.3131: Reschedule plant operations or reduce load to avoid peaks | $20,015 | - |
$20,015
-
kWh
|
|
| 09 | 2.4236: Eliminate leaks in inert gas and compressed air lines/ valves | $3,296 | $550 |
$3,296
47,773
kWh
|
|
| TOTAL RECOMMENDED | $42,918 | $57,434 |
$42,918
332,065
kWh
|
||
| TOTAL IMPLEMENTED | $6,204 | $2,997 |
$6,204
89,977
kWh
|
||
| Yearly Savings* | Imp'd Cost* | Electricity Usage Savings | |||
*Savings and costs are best estimates based on the center's site visit, associated engineering analysis, and typical capital and labor costs