ITAC Assessment: UF0033
ITAC logo
ITAC Assessment: UF0033
Grant Funding Opportunity NOW OPEN
Up to $300k at 50% cost share for qualifying* projects.
Grant Funding Opportunity Open
Qualifying* small and medium-sized US manufacturers, that received an ITAC, Onsite Energy/CHP TAP, or qualified equivalent assessment since 2018 can now apply for grants for implementation of assessment recommendations at up to 50% of qualifying* project costs with a maximum of $300,000 per grant.
IMPORTANT: The grant program now operates on a rolling basis and applications may be submitted at any time through the year, with quarterly reviews.
*See Full Grant Solicitation for full qualification and selection details.
Assessment Year 1992
Principal Product NEWSPAPERS
NAICS
n/a
SIC 2711: Newspapers: Publishing, or Publishing and Printing
Sales Range $10
M
to 50
M
# of Employees 230
Plant Area
n/a
Annual Production 250,000,000
pieces
Production Hrs. Annual 8,736
hrs
Location (State) Florida

Facility Energy Cost and Usage

Source Yearly Cost Usage
Electricity Usage $293,213 3,967,175
kWh
TOTAL YEARLY COSTS -
RECOMMENDED SAVINGS* $41,189 *Non-energy impacts included in savings.
IMPLEMENTED SAVINGS* -

Recommendations

# Description Yearly Savings* Imp'd Cost* Status Electricity Usage Savings Administrative Changes Savings
01 2.7142: Utilize higher efficiency lamps and/or ballasts $765 $327 $765
9,379
kWh
-
02 2.7142: Utilize higher efficiency lamps and/or ballasts $7,972 $29,120 - $7,972
03 2.7142: Utilize higher efficiency lamps and/or ballasts $2,098 $287 $2,098
26,671
kWh
-
04 2.7233: Use properly designed and sized hvac equipment $14,800 $120,000 $14,800
199,883
kWh
-
05 2.4133: Use most efficient type of electric motors $1,577 $7,504 $1,577
21,395
kWh
-
06 2.4221: Install compressor air intakes in coolest locations $641 $200 $641
8,792
kWh
-
07 2.7226: Use computer programs to optimize hvac performance $13,336 $7,000 $13,336
409,437
kWh
-
TOTAL RECOMMENDED $41,189 $164,438 $33,217
675,557
kWh
$7,972
TOTAL IMPLEMENTED - - - -
Yearly Savings* Imp'd Cost* Electricity Usage Savings Administrative Changes Savings
*Savings and costs are best estimates based on the center's site visit, associated engineering analysis, and typical capital and labor costs