Assessment Year | 1991 |
---|---|
Principal Product | TRACK & ROTARY DRILLS |
NAICS |
n/a
|
SIC | 3532: Mining Machinery and Equipment, Except Oil and Gas Field Machinery and Equipment |
Sales Range | $10 M to 50M |
# of Employees | 250 |
Plant Area |
n/a
|
Annual Production | 140
pieces
|
Production Hrs. Annual | 4,420
hrs
|
Location (State) | Florida |
Facility Energy Cost and Usage
Source | Yearly Cost | Usage | Unit Cost | |
---|---|---|---|---|
Electricity Usage | $173,248 | 2,118,406 |
kWh
|
$0.082 |
TOTAL YEARLY COSTS | - | |||
RECOMMENDED SAVINGS* | $39,282 |
See individual recommendations below
*Non-energy impacts included in savings.
|
||
IMPLEMENTED SAVINGS* | $39,282 |
Recommendations
# | Description | Yearly Savings* | Imp'd Cost* | Status | Electricity Usage Savings |
---|---|---|---|---|---|
01 | 2.7142: Utilize higher efficiency lamps and/or ballasts | $2,788 | $2,118 |
$2,788
33,998
kWh
|
|
02 | 2.7123: Keep lamps and reflectors clean | $9,472 | $3,600 |
$9,472
115,768
kWh
|
|
03 | 2.6232: Install set-back timers | $3,111 | $288 |
$3,111
38,101
kWh
|
|
04 | 2.7111: Reduce illumination to minimum necessary levels | $2,464 | - |
$2,464
30,188
kWh
|
|
05 | 2.4133: Use most efficient type of electric motors | $251 | $2,520 |
$251
2,931
kWh
|
|
06 | 2.7233: Use properly designed and sized hvac equipment | $6,167 | $5,300 |
$6,167
75,615
kWh
|
|
07 | 2.3131: Reschedule plant operations or reduce load to avoid peaks | $15,029 | - |
$15,029
-
kWh
|
|
TOTAL RECOMMENDED | $39,282 | $13,826 |
$39,282
296,601
kWh
|
||
TOTAL IMPLEMENTED | $39,282 | $13,826 |
$39,282
296,601
kWh
|
||
Yearly Savings* | Imp'd Cost* | Electricity Usage Savings |
*Savings and costs are best estimates based on the center's site visit, associated engineering analysis, and typical capital and labor costs