| Assessment Year | 2026 |
|---|---|
| Principal Product | Welded metal rings and flash butt |
| NAICS | 336412: Aircraft Engine and Engine Parts Manufacturing |
| SIC | 3724: Aircraft Engines and Engine Parts |
| Sales Range | $5 M to 10M |
| # of Employees | 85 |
| Plant Area |
250,000
ft2
|
| Annual Production | 8,220,940
units
|
| Production Hrs. Annual | 2,400
hrs
|
| Location (State) | Ohio |
Facility Energy Cost and Usage
| Source | Yearly Cost | Usage | Unit Cost | ||
|---|---|---|---|---|---|
| Electricity Usage | $160,011 | 1,573,968 |
kWh
|
$0.10 | |
| Electricity Demand | $18,008 | 6,367 |
kW-mo/yr
|
$2.83 | |
| Electricity Fees | $7,612 | - |
|
- | |
| Natural Gas | $266,781 | 51,229 |
MMBtu
|
$5.21 | |
| Waste Disposal Costs | |||||
| Water Usage | $6,105 | 1,213 |
Tgal
|
$5.03 | |
| Water Disposal | $21,362 | 1,213 |
Tgal
|
$17.61 | |
| Other Liquid (non-haz) | $15,199 | 1 |
gal
|
$15,199.00 | |
| TOTAL YEARLY COSTS | $495,078 | ||||
| RECOMMENDED SAVINGS* | $68,889 |
See individual recommendations below
*Non-energy impacts included in savings.
|
|||
| IMPLEMENTED SAVINGS* | - | ||||
Recommendations
| # | Description | Yearly Savings* | Imp'd Cost* | Status | Electricity Usage Savings | Electricity Demand Savings | Electricity Fees Savings | Natural Gas Savings | Primary Raw Material Savings | One-time Revenue or Avoided Cost Savings |
|---|---|---|---|---|---|---|---|---|---|---|
| 01 | 2.4324: Replace hydraulic / pneumatic equipment with electric equipment | $15,174 | $7,053 |
$15,174
149,200
kWh
|
- | - | - | - | - | |
| 02 | 2.4231: Reduce the pressure of compressed air to the minimum required | $4,216 | $5,253 |
$3,701
36,387
kWh
|
$515
-
kW-mo/yr
|
- | - | - | - | |
| 03 | 2.4236: Eliminate leaks in inert gas and compressed air lines/ valves | $1,613 | $953 |
$1,416
13,925
kWh
|
$197
-
kW-mo/yr
|
- | - | - | - | |
| 04 | 2.7447: Install vinyl strip / high speed / air curtain doors | $3,493 | $3,900 | - | - | - |
$3,493
-
MMBtu
|
- | - | |
| 05 | 2.2414: Use waste heat from hot flue gases to preheat | $14,966 | $24,590 | - | - | - |
$14,966
-
MMBtu
|
- | - | |
| 06 | 2.7142: Utilize higher efficiency lamps and/or ballasts | $23,994 | $72,403 |
$16,121
158,515
kWh
|
$2,242
-
kW-mo/yr
|
- | - | $2,175 | $3,456 | |
| 07 | 2.7135: Install occupancy sensors | $485 | $513 |
$485
4,277
kWh
|
- | - | - | - | - | |
| 08 | 2.3212: Optimize plant power factor | $4,948 | $16,499 | - | - | $4,948 | - | - | - | |
| TOTAL RECOMMENDED | $68,889 | $131,164 |
$36,897
362,304
kWh
|
$2,954
-
kW-mo/yr
|
$4,948 |
$18,459
-
MMBtu
|
$2,175 | $3,456 | ||
| TOTAL IMPLEMENTED | - | - | - | - | - | - | - | - | ||
| Yearly Savings* | Imp'd Cost* | Electricity Usage Savings | Electricity Demand Savings | Electricity Fees Savings | Natural Gas Savings | Primary Raw Material Savings | One-time Revenue or Avoided Cost Savings | |||
*Savings and costs are best estimates based on the center's site visit, associated engineering analysis, and typical capital and labor costs