| Assessment Year | 2026 |
|---|---|
| Principal Product | Cylinders |
| NAICS | 332420: Metal Tank (Heavy Gauge) Manufacturing |
| SIC | 3443: Fabricated Plate Work (Boiler Shops) |
| Sales Range | $100 M to 500M |
| # of Employees | 382 |
| Plant Area |
134,150
ft2
|
| Annual Production | 8,220,940
units
|
| Production Hrs. Annual | 8,160
hrs
|
| Location (State) | Ohio |
Facility Energy Cost and Usage
| Source | Yearly Cost | Usage | Unit Cost | ||
|---|---|---|---|---|---|
| Electricity Usage | $699,253 | 12,072,975 |
kWh
|
$0.058 | |
| Electricity Demand | $290,102 | 24,235 |
kW-mo/yr
|
$11.97 | |
| Natural Gas | $264,649 | 41,923 |
MMBtu
|
$6.31 | |
| Waste Disposal Costs | |||||
| Water Usage | $23,544 | 5,401 |
Tgal
|
$4.36 | |
| Water Disposal | $41,074 | 5,195 |
Tgal
|
$7.91 | |
| Other Liquid (non-haz) | $19,631 | 1 |
gal
|
$19,631.00 | |
| TOTAL YEARLY COSTS | $1,338,253 | ||||
| RECOMMENDED SAVINGS* | $50,012 |
See individual recommendations below
*Non-energy impacts included in savings.
|
|||
| IMPLEMENTED SAVINGS* | - | ||||
Recommendations
| # | Description | Yearly Savings* | Imp'd Cost* | Status | Electricity Usage Savings | Electricity Demand Savings | Natural Gas Savings |
|---|---|---|---|---|---|---|---|
| 01 | 2.4111: Utilize energy-efficient belts and other improved mechanisms | $968 | - |
$742
12,822
kWh
|
$226
-
kW-mo/yr
|
- | |
| 02 | 2.7447: Install vinyl strip / high speed / air curtain doors | $3,886 | $1,240 | - | - |
$3,886
-
MMBtu
|
|
| 03 | 2.7442: Keep doors and windows shut when not on use | $1,148 | - | - | - |
$1,148
-
MMBtu
|
|
| 04 | 2.4311: Recover mechanical energy | $35,850 | $12,765 |
$27,492
474,814
kWh
|
$8,358
-
kW-mo/yr
|
- | |
| 05 | 2.4236: Eliminate leaks in inert gas and compressed air lines/ valves | $8,160 | $953 |
$5,391
77,570
kWh
|
$2,769
-
kW-mo/yr
|
- | |
| TOTAL RECOMMENDED | $50,012 | $14,958 |
$33,625
565,206
kWh
|
$11,353
-
kW-mo/yr
|
$5,034
-
MMBtu
|
||
| TOTAL IMPLEMENTED | - | - | - | - | - | ||
*Savings and costs are best estimates based on the center's site visit, associated engineering analysis, and typical capital and labor costs