ITAC Assessment: UD1132
ITAC logo
ITAC Assessment: UD1132
Grant Funding Opportunity NOW OPEN
Up to $300k at 50% cost share for qualifying* projects.
Grant Funding Opportunity Open
Qualifying* small and medium-sized US manufacturers, that received an ITAC, Onsite Energy/CHP TAP, or qualified equivalent assessment since 2018 can now apply for grants for implementation of assessment recommendations at up to 50% of qualifying* project costs with a maximum of $300,000 per grant.
IMPORTANT: The grant program now operates on a rolling basis and applications may be submitted at any time through the year, with quarterly reviews.
*See Full Grant Solicitation for full qualification and selection details.
Assessment Year 2026
Principal Product Cylinders
NAICS 332420: Metal Tank (Heavy Gauge) Manufacturing
SIC 3443: Fabricated Plate Work (Boiler Shops)
Sales Range $100
M
to 500
M
# of Employees 382
Plant Area 134,150
ft2
Annual Production 8,220,940
units
Production Hrs. Annual 8,160
hrs
Location (State) Ohio

Facility Energy Cost and Usage

Source Yearly Cost Usage
Electricity Usage $699,253 12,072,975
kWh
Electricity Demand $290,102 24,235
kW-mo/yr
Natural Gas $264,649 41,923
MMBtu
Waste Disposal Costs
Water Usage $23,544 5,401
Tgal
Water Disposal $41,074 5,195
Tgal
Other Liquid (non-haz) $19,631 1
gal
TOTAL YEARLY COSTS $1,338,253
RECOMMENDED SAVINGS* $50,012 *Non-energy impacts included in savings.
IMPLEMENTED SAVINGS* -

Recommendations

# Description Yearly Savings* Imp'd Cost* Status Electricity Usage Savings Electricity Demand Savings Natural Gas Savings
01 2.4111: Utilize energy-efficient belts and other improved mechanisms $968 - $742
12,822
kWh
$226
-
kW-mo/yr
-
02 2.7447: Install vinyl strip / high speed / air curtain doors $3,886 $1,240 - - $3,886
-
MMBtu
03 2.7442: Keep doors and windows shut when not on use $1,148 - - - $1,148
-
MMBtu
04 2.4311: Recover mechanical energy $35,850 $12,765 $27,492
474,814
kWh
$8,358
-
kW-mo/yr
-
05 2.4236: Eliminate leaks in inert gas and compressed air lines/ valves $8,160 $953 $5,391
77,570
kWh
$2,769
-
kW-mo/yr
-
TOTAL RECOMMENDED $50,012 $14,958 $33,625
565,206
kWh
$11,353
-
kW-mo/yr
$5,034
-
MMBtu
TOTAL IMPLEMENTED - - - - -
*Savings and costs are best estimates based on the center's site visit, associated engineering analysis, and typical capital and labor costs