| Assessment Year | 2026 |
|---|---|
| Principal Product | Household Cleaning, Cosmetics, Adhesives, and Personal Care Products |
| NAICS | 325520: Adhesive Manufacturing |
| SIC | 2891: Adhesives and Sealants |
| Sales Range | $100 M to 500M |
| # of Employees | 150 |
| Plant Area |
196,000
ft2
|
| Annual Production | 40,000,000
units
|
| Production Hrs. Annual | 6,888
hrs
|
| Location (State) | Ohio |
Facility Energy Cost and Usage
| Source | Yearly Cost | Usage | Unit Cost | ||
|---|---|---|---|---|---|
| Electricity Usage | $442,371 | 7,682,064 |
kWh
|
$0.058 | |
| Electricity Demand | $260,820 | 15,842 |
kW-mo/yr
|
$16.46 | |
| Electricity Fees | $3,350 | - |
|
- | |
| Natural Gas | $137,209 | 17,587 |
MMBtu
|
$7.80 | |
| Waste Disposal Costs | |||||
| Water Usage | $9,439 | 300 |
Tgal
|
$31.46 | |
| TOTAL YEARLY COSTS | $853,189 | ||||
| RECOMMENDED SAVINGS* | $103,697 |
See individual recommendations below
*Non-energy impacts included in savings.
|
|||
| IMPLEMENTED SAVINGS* | - | ||||
Recommendations
| # | Description | Yearly Savings* | Imp'd Cost* | Status | Electricity Usage Savings | Electricity Demand Savings | Natural Gas Savings | Other Gas Savings | Personnel Changes Savings | Primary Raw Material Savings |
|---|---|---|---|---|---|---|---|---|---|---|
| 01 | 2.8114: Change rate schedules or other changes in utility service | $29,465 | - | - | - | - |
$29,465
-
MMBtu
|
- | - | |
| 02 | 2.4146: Use adjustable frequency drive or multiple speed motors on existing system | $24,321 | - |
$16,236
281,880
kWh
|
$8,085
-
kW-mo/yr
|
- | - | - | - | |
| 03 | 2.7133: Use separate switches on perimeter lighting which may be turned off when natural light is available | $2,524 | - |
$775
13,478
kWh
|
$1,067
-
kW-mo/yr
|
- | - | $647 | $35 | |
| 04 | 2.7314: Reduce ventilation air | $31,291 | - | - | - |
$31,291
-
MMBtu
|
- | - | - | |
| 05 | 2.7447: Install vinyl strip / high speed / air curtain doors | $172 | $600 | - | - |
$172
-
MMBtu
|
- | - | - | |
| 06 | 2.4239: Eliminate or reduce compressed air usage | $8,922 | - |
$8,922
155,168
kWh
|
- | - | - | - | - | |
| 07 | 2.4236: Eliminate leaks in inert gas and compressed air lines/ valves | $7,002 | $828 |
$4,684
80,843
kWh
|
$2,318
-
kW-mo/yr
|
- | - | - | - | |
| TOTAL RECOMMENDED | $103,697 | $1,428 |
$30,617
531,369
kWh
|
$11,470
-
kW-mo/yr
|
$31,463
-
MMBtu
|
$29,465
-
MMBtu
|
$647 | $35 | ||
| TOTAL IMPLEMENTED | - | - | - | - | - | - | - | - | ||
| Yearly Savings* | Imp'd Cost* | Electricity Usage Savings | Electricity Demand Savings | Natural Gas Savings | Other Gas Savings | Personnel Changes Savings | Primary Raw Material Savings | |||
*Savings and costs are best estimates based on the center's site visit, associated engineering analysis, and typical capital and labor costs