| Assessment Year | 2025 |
|---|---|
| Principal Product | Warehousing, Packing, Spray Drying, and Transportation services |
| NAICS | 339999: All Other Miscellaneous Manufacturing |
| SIC | 3999: Manufacturing Industries, Not Elsewhere Classified |
| Sales Range | $10 M to 50M |
| # of Employees | 80 |
| Plant Area |
310,000
ft2
|
| Annual Production | 1,001
units
|
| Production Hrs. Annual | 2,000
hrs
|
| Location (State) | Ohio |
Facility Energy Cost and Usage
| Source | Yearly Cost | Usage | Unit Cost | ||
|---|---|---|---|---|---|
| Electricity Usage | $85,898 | 884,800 |
kWh
|
$0.097 | |
| Electricity Demand | $11,931 | 1,885 |
kW-mo/yr
|
$6.33 | |
| Electricity Fees | $2,542 | - |
|
- | |
| Natural Gas | $50,034 | 4,220 |
MMBtu
|
$11.86 | |
| Waste Disposal Costs | |||||
| Water Usage | $873 | 92 |
Tgal
|
$9.49 | |
| Water Disposal | $873 | 92 |
Tgal
|
$9.49 | |
| Other Liquid (non-haz) | $2,841 | 1 |
gal
|
$2,841.00 | |
| TOTAL YEARLY COSTS | $154,992 | ||||
| RECOMMENDED SAVINGS* | $18,410 |
See individual recommendations below
*Non-energy impacts included in savings.
|
|||
| IMPLEMENTED SAVINGS* | - | ||||
Recommendations
| # | Description | Yearly Savings* | Imp'd Cost* | Status | Electricity Usage Savings | Electricity Demand Savings | Natural Gas Savings | One-time Revenue or Avoided Cost Savings |
|---|---|---|---|---|---|---|---|---|
| 01 | 2.3132: Recharge batteries on during off-peak demand periods | $2,950 | - | - |
$2,950
-
kW-mo/yr
|
- | - | |
| 02 | 2.4231: Reduce the pressure of compressed air to the minimum required | $165 | - |
$84
866
kWh
|
$81
-
kW-mo/yr
|
- | - | |
| 03 | 2.7233: Use properly designed and sized hvac equipment | $9,836 | $1,500 |
$9,019
92,888
kWh
|
$817
-
kW-mo/yr
|
- | - | |
| 04 | 2.7447: Install vinyl strip / high speed / air curtain doors | $198 | $375 | - | - |
$198
-
MMBtu
|
- | |
| 05 | 2.7142: Utilize higher efficiency lamps and/or ballasts | $5,261 | $6,149 |
$3,590
36,972
kWh
|
$1,404
-
kW-mo/yr
|
- | $267 | |
| TOTAL RECOMMENDED | $18,410 | $8,024 |
$12,693
130,726
kWh
|
$5,252
-
kW-mo/yr
|
$198
-
MMBtu
|
$267 | ||
| TOTAL IMPLEMENTED | - | - | - | - | - | - | ||
*Savings and costs are best estimates based on the center's site visit, associated engineering analysis, and typical capital and labor costs