Assessment Year | 2025 |
---|---|
Principal Product | Automotive Parts |
NAICS | 336390: Other Motor Vehicle Parts Manufacturing |
SIC | 3714: Motor Vehicle Parts and Accessories |
Sales Range | $100 M to 500M |
# of Employees | 650 |
Plant Area |
619,000
ft2
|
Annual Production | 1,001
pieces
|
Production Hrs. Annual | 6,240
hrs
|
Location (State) | Ohio |
Facility Energy Cost and Usage
Source | Yearly Cost | Usage | Unit Cost | ||
---|---|---|---|---|---|
Electricity Usage | $956,371 | 21,820,272 |
kWh
|
$0.044 | |
Electricity Demand | $65,421 | 40,809 |
kW-mo/yr
|
$1.60 | |
Electricity Fees | $34,618 | - |
|
- | |
Natural Gas | $118,159 | 44,209 |
MMBtu
|
$2.67 | |
Waste Disposal Costs | |||||
Water Usage | $81,918 | 15,275 |
Tgal
|
$5.36 | |
TOTAL YEARLY COSTS | $1,256,487 | ||||
RECOMMENDED SAVINGS* | $74,481 |
See individual recommendations below
*Non-energy impacts included in savings.
|
|||
IMPLEMENTED SAVINGS* | - |
Recommendations
# | Description | Yearly Savings* | Imp'd Cost* | Status | Electricity Usage Savings | Electricity Demand Savings | Electricity Fees Savings | Natural Gas Savings |
---|---|---|---|---|---|---|---|---|
01 | 2.4146: Use adjustable frequency drive or multiple speed motors on existing system | $6,358 | - |
$5,940
135,614
kWh
|
$418
-
kW-mo/yr
|
- | - | |
02 | 2.4146: Use adjustable frequency drive or multiple speed motors on existing system | $3,072 | $1,464 |
$2,868
65,475
kWh
|
$204
-
kW-mo/yr
|
- | - | |
03 | 2.4146: Use adjustable frequency drive or multiple speed motors on existing system | $2,927 | $8,803 |
$2,553
58,285
kWh
|
$374
-
kW-mo/yr
|
- | - | |
04 | 2.6212: Turn off equipment during breaks, reduce operating time | $961 | - |
$961
21,932
kWh
|
- | - | - | |
05 | 2.4239: Eliminate or reduce compressed air usage | $11,733 | $17,500 |
$11,733
267,874
kWh
|
- | - | - | |
06 | 2.4221: Install compressor air intakes in coolest locations | $11,326 | $4,060 |
$10,573
241,383
kWh
|
$753
-
kW-mo/yr
|
- | - | |
07 | 2.4236: Eliminate leaks in inert gas and compressed air lines/ valves | $2,182 | $953 |
$2,039
46,550
kWh
|
$143
-
kW-mo/yr
|
- | - | |
08 | 2.2437: Recover waste heat from equipment | $8,078 | $19,900 |
$(-128.0)
(-2,919)
kWh
|
$(-9.0)
-
kW-mo/yr
|
- |
$8,215
-
MMBtu
|
|
09 | 2.3212: Optimize plant power factor | $27,844 | $76,225 | - | - | $27,844 | - | |
TOTAL RECOMMENDED | $74,481 | $128,905 |
$36,539
834,194
kWh
|
$1,883
-
kW-mo/yr
|
$27,844 |
$8,215
-
MMBtu
|
||
TOTAL IMPLEMENTED | - | - | - | - | - | - | ||
Yearly Savings* | Imp'd Cost* | Electricity Usage Savings | Electricity Demand Savings | Electricity Fees Savings | Natural Gas Savings |
*Savings and costs are best estimates based on the center's site visit, associated engineering analysis, and typical capital and labor costs