Assessment Year | 2024 |
---|---|
Principal Product | Industrial fans |
NAICS | 333413: Industrial and Commercial Fan and Blower and Air Purification Equipment Manufacturing |
SIC | 3564: Industrial and Commercial Fans and Blowers and Air Purification Equipment |
Sales Range | $50 M to 100M |
# of Employees | 114 |
Plant Area |
87,000
ft2
|
Annual Production | 31,413
units
|
Production Hrs. Annual | 2,168
hrs
|
Location (State) | Ohio |
Facility Energy Cost and Usage
Source | Yearly Cost | Usage | Unit Cost | ||
---|---|---|---|---|---|
Electricity Usage | $91,617 | 1,173,709 |
kWh
|
$0.078 | |
Electricity Demand | $35,930 | 5,157 |
kW-mo/yr
|
$6.97 | |
Electricity Fees | $4,748 | - |
|
- | |
Natural Gas | $9,911 | 6,421 |
MMBtu
|
$1.54 | |
Other Gas | $2,574 | 1 |
MMBtu
|
$2,574.00 | |
Waste Disposal Costs | |||||
Water Usage | $2,076 | 400 |
Tgal
|
$5.19 | |
Water Disposal | $2,514 | 400 |
Tgal
|
$6.29 | |
TOTAL YEARLY COSTS | $149,370 | ||||
RECOMMENDED SAVINGS* | $10,363 |
See individual recommendations below
*Non-energy impacts included in savings.
|
|||
IMPLEMENTED SAVINGS* | - |
Recommendations
# | Description | Yearly Savings* | Imp'd Cost* | Status | Electricity Usage Savings | Electricity Demand Savings | Electricity Fees Savings | Natural Gas Savings | Personnel Changes Savings | Ancillary Material Cost Savings |
---|---|---|---|---|---|---|---|---|---|---|
01 | 2.4239: Eliminate or reduce compressed air usage | $2,975 | - |
$2,095
26,827
kWh
|
$880
-
kW-mo/yr
|
- | - | - | - | |
02 | 2.4236: Eliminate leaks in inert gas and compressed air lines/ valves | $1,335 | $1,068 |
$894
11,441
kWh
|
$441
-
kW-mo/yr
|
- | - | - | - | |
03 | 2.4231: Reduce the pressure of compressed air to the minimum required | $684 | - |
$458
5,876
kWh
|
$226
-
kW-mo/yr
|
- | - | - | - | |
04 | 2.4221: Install compressor air intakes in coolest locations | $452 | $487 |
$319
4,081
kWh
|
$133
-
kW-mo/yr
|
- | - | - | - | |
05 | 2.3212: Optimize plant power factor | $3,614 | $6,258 | - |
$177
-
kW-mo/yr
|
$3,437 | - | - | - | |
06 | 2.7135: Install occupancy sensors | $399 | $1,254 |
$358
4,590
kWh
|
- | - | - | $34 | $7 | |
07 | 2.7111: Reduce illumination to minimum necessary levels | $303 | $900 |
$203
2,601
kWh
|
$100
-
kW-mo/yr
|
- | - | - | - | |
08 | 2.7224: Reduce space conditioning during non-working hours | $601 | $2,093 | - | - | - |
$601
-
MMBtu
|
- | - | |
TOTAL RECOMMENDED | $10,363 | $12,060 |
$4,327
55,416
kWh
|
$1,957
-
kW-mo/yr
|
$3,437 |
$601
-
MMBtu
|
$34 | $7 | ||
TOTAL IMPLEMENTED | - | - | - | - | - | - | - | - | ||
Yearly Savings* | Imp'd Cost* | Electricity Usage Savings | Electricity Demand Savings | Electricity Fees Savings | Natural Gas Savings | Personnel Changes Savings | Ancillary Material Cost Savings |
*Savings and costs are best estimates based on the center's site visit, associated engineering analysis, and typical capital and labor costs