ITAC Assessment: UD1062
ITAC logo
ITAC Assessment: UD1062
Grant Funding Opportunity NOW OPEN
Up to $300k at 50% cost share for qualifying* projects.
Grant Funding Opportunity Open
Qualifying* small and medium-sized US manufacturers, that received an ITAC, Onsite Energy/CHP TAP, or qualified equivalent assessment since 2018 can now apply for grants for implementation of assessment recommendations at up to 50% of qualifying* project costs with a maximum of $300,000 per grant.
IMPORTANT: The grant program now operates on a rolling basis and applications may be submitted at any time through the year, with quarterly reviews.
*See Full Grant Solicitation for full qualification and selection details.
Assessment Year 2023
Principal Product Polymer Sealants
NAICS 325211: Plastics Material and Resin Manufacturing
SIC 2891: Adhesives and Sealants
Sales Range $10
M
to 50
M
# of Employees 100
Plant Area 33,000
ft2
Annual Production 27,400,000
units
Production Hrs. Annual 6,240
hrs
Location (State) Ohio

Facility Energy Cost and Usage

Source Yearly Cost Usage
Electricity Usage $107,103 2,235,415
kWh
Electricity Demand $40,941 6,208
kW-mo/yr
Electricity Fees $346 -
Natural Gas $27,157 1,841
MMBtu
Waste Disposal Costs
Water Usage $5,117 1,243
Tgal
Water Disposal $5,618 1,243
Tgal
Other Liquid (non-haz) $1,706 1
gal
TOTAL YEARLY COSTS $187,988
RECOMMENDED SAVINGS* $10,319 *Non-energy impacts included in savings.
IMPLEMENTED SAVINGS* $1,152

Recommendations

# Description Yearly Savings* Imp'd Cost* Status Electricity Usage Savings Electricity Demand Savings Water Disposal Savings Administrative Changes Savings
01 2.6212: Turn off equipment during breaks, reduce operating time $5,907 - $4,674
97,182
kWh
$1,233
-
kW-mo/yr
- -
02 2.3131: Reschedule plant operations or reduce load to avoid peaks $1,486 - - $1,486
-
kW-mo/yr
- -
03 3.4116: Meter recycled water (to reduce sewer charges) $705 $260 - - $705
-
Tgal
-
04 2.4236: Eliminate leaks in inert gas and compressed air lines/ valves $727 $952 $575
11,966
kWh
$152
-
kW-mo/yr
- -
05 2.4221: Install compressor air intakes in coolest locations $342 - $271
5,634
kWh
$71
-
kW-mo/yr
- -
06 2.7135: Install occupancy sensors $1,152 $2,000 $619
12,867
kWh
- - $533
TOTAL RECOMMENDED $10,319 $3,212 $6,139
127,649
kWh
$2,942
-
kW-mo/yr
$705
-
Tgal
$533
TOTAL IMPLEMENTED $1,152 $2,000 $619
12,867
kWh
- - $533
Yearly Savings* Imp'd Cost* Electricity Usage Savings Electricity Demand Savings Water Disposal Savings Administrative Changes Savings
*Savings and costs are best estimates based on the center's site visit, associated engineering analysis, and typical capital and labor costs