Assessment Year | 2023 |
---|---|
Principal Product | Polymer Sealants |
NAICS | 325211: Plastics Material and Resin Manufacturing |
SIC | 2891: Adhesives and Sealants |
Sales Range | $10 M to 50M |
# of Employees | 100 |
Plant Area |
33,000
ft2
|
Annual Production | 27,400,000
units
|
Production Hrs. Annual | 6,240
hrs
|
Location (State) | Ohio |
Facility Energy Cost and Usage
Source | Yearly Cost | Usage | Unit Cost | ||
---|---|---|---|---|---|
Electricity Usage | $107,103 | 2,235,415 |
kWh
|
$0.048 | |
Electricity Demand | $40,941 | 6,208 |
kW-mo/yr
|
$6.59 | |
Electricity Fees | $346 | - |
|
- | |
Natural Gas | $27,157 | 1,841 |
MMBtu
|
$14.75 | |
Waste Disposal Costs | |||||
Water Usage | $5,117 | 1,243 |
Tgal
|
$4.12 | |
Water Disposal | $5,618 | 1,243 |
Tgal
|
$4.52 | |
Other Liquid (non-haz) | $1,706 | 1 |
gal
|
$1,706.00 | |
TOTAL YEARLY COSTS | $187,988 | ||||
RECOMMENDED SAVINGS* | $10,319 |
See individual recommendations below
*Non-energy impacts included in savings.
|
|||
IMPLEMENTED SAVINGS* | $1,152 |
Recommendations
# | Description | Yearly Savings* | Imp'd Cost* | Status | Electricity Usage Savings | Electricity Demand Savings | Water Disposal Savings | Administrative Changes Savings |
---|---|---|---|---|---|---|---|---|
01 | 2.6212: Turn off equipment during breaks, reduce operating time | $5,907 | - |
$4,674
97,182
kWh
|
$1,233
-
kW-mo/yr
|
- | - | |
02 | 2.3131: Reschedule plant operations or reduce load to avoid peaks | $1,486 | - | - |
$1,486
-
kW-mo/yr
|
- | - | |
03 | 3.4116: Meter recycled water (to reduce sewer charges) | $705 | $260 | - | - |
$705
-
Tgal
|
- | |
04 | 2.4236: Eliminate leaks in inert gas and compressed air lines/ valves | $727 | $952 |
$575
11,966
kWh
|
$152
-
kW-mo/yr
|
- | - | |
05 | 2.4221: Install compressor air intakes in coolest locations | $342 | - |
$271
5,634
kWh
|
$71
-
kW-mo/yr
|
- | - | |
06 | 2.7135: Install occupancy sensors | $1,152 | $2,000 |
$619
12,867
kWh
|
- | - | $533 | |
TOTAL RECOMMENDED | $10,319 | $3,212 |
$6,139
127,649
kWh
|
$2,942
-
kW-mo/yr
|
$705
-
Tgal
|
$533 | ||
TOTAL IMPLEMENTED | $1,152 | $2,000 |
$619
12,867
kWh
|
- | - | $533 | ||
Yearly Savings* | Imp'd Cost* | Electricity Usage Savings | Electricity Demand Savings | Water Disposal Savings | Administrative Changes Savings |
*Savings and costs are best estimates based on the center's site visit, associated engineering analysis, and typical capital and labor costs