ITAC Assessment: UD1058
ITAC logo
ITAC Assessment: UD1058
Grant Funding Opportunity NOW OPEN
Up to $300k at 50% cost share for qualifying* projects.
Grant Funding Opportunity Open
Qualifying* small and medium-sized US manufacturers, that received an ITAC, Onsite Energy/CHP TAP, or qualified equivalent assessment since 2018 can now apply for grants for implementation of assessment recommendations at up to 50% of qualifying* project costs with a maximum of $300,000 per grant.
IMPORTANT: The grant program now operates on a rolling basis and applications may be submitted at any time through the year, with quarterly reviews.
*See Full Grant Solicitation for full qualification and selection details.
Assessment Year 2023
Principal Product Air and Gas Compressors
NAICS 333912: Air and Gas Compressor Manufacturing
SIC 3563: Air and Gas Compressors
Sales Range $50
M
to 100
M
# of Employees 125
Plant Area 250,000
ft2
Annual Production 584
units
Production Hrs. Annual 8,760
hrs
Location (State) Ohio

Facility Energy Cost and Usage

Source Yearly Cost Usage
Electricity Usage $230,292 2,559,352
kWh
Electricity Demand $63,498 12,551
kW-mo/yr
Electricity Fees $7,183 -
Natural Gas $85,183 17,259
MMBtu
Waste Disposal Costs
Water Usage $20,549 3,130
Tgal
Water Disposal $11,718 3,130
Tgal
Other Liquid (non-haz) $7,825 1
gal
TOTAL YEARLY COSTS $426,248
RECOMMENDED SAVINGS* $79,334 *Non-energy impacts included in savings.
IMPLEMENTED SAVINGS* $42,225

Recommendations

# Description Yearly Savings* Imp'd Cost* Status Electricity Usage Savings Electricity Demand Savings Natural Gas Savings Personnel Changes Savings Ancillary Material Cost Savings
01 2.3131: Reschedule plant operations or reduce load to avoid peaks $23,188 - - $23,188
-
kW-mo/yr
- - -
02 2.3131: Reschedule plant operations or reduce load to avoid peaks $282 - - $282
-
kW-mo/yr
- - -
03 2.4111: Utilize energy-efficient belts and other improved mechanisms $329 - $299
3,325
kWh
$30
-
kW-mo/yr
- - -
04 2.4239: Eliminate or reduce compressed air usage $10,990 $11,117 $10,204
113,382
kWh
$786
-
kW-mo/yr
- - -
05 2.4236: Eliminate leaks in inert gas and compressed air lines/ valves $7,636 $952 $7,090
78,772
kWh
$546
-
kW-mo/yr
- - -
06 2.7447: Install vinyl strip / high speed / air curtain doors $1,653 $1,115 - - $1,653
-
MMBtu
- -
07 2.7142: Utilize higher efficiency lamps and/or ballasts $34,307 $29,827 $19,340
215,040
kWh
$1,490
-
kW-mo/yr
- $3,556 $9,921
08 2.7135: Install occupancy sensors $949 $290 $694
7,677
kWh
$159
-
kW-mo/yr
- $19 $77
TOTAL RECOMMENDED $79,334 $43,301 $37,627
418,196
kWh
$26,481
-
kW-mo/yr
$1,653
-
MMBtu
$3,575 $9,998
TOTAL IMPLEMENTED $42,225 $30,779 $26,430
293,812
kWh
$2,318
-
kW-mo/yr
- $3,556 $9,921
Yearly Savings* Imp'd Cost* Electricity Usage Savings Electricity Demand Savings Natural Gas Savings Personnel Changes Savings Ancillary Material Cost Savings
*Savings and costs are best estimates based on the center's site visit, associated engineering analysis, and typical capital and labor costs