ITAC Assessment: UD1049
ITAC logo
ITAC Assessment: UD1049
Grant Funding Opportunity NOW OPEN
Up to $300k at 50% cost share for qualifying* projects.
Grant Funding Opportunity Open
Qualifying* small and medium-sized US manufacturers, that received an ITAC, Onsite Energy/CHP TAP, or qualified equivalent assessment since 2018 can now apply for grants for implementation of assessment recommendations at up to 50% of qualifying* project costs with a maximum of $300,000 per grant.
IMPORTANT: The grant program now operates on a rolling basis and applications may be submitted at any time through the year, with quarterly reviews.
*See Full Grant Solicitation for full qualification and selection details.
Assessment Year 2023
Principal Product Appliance control panels and semi-truck bumpers
NAICS 336370: Motor Vehicle Metal Stamping
SIC 3469: Metal Stampings, Not Elsewhere Classified
Sales Range $50
M
to 100
M
# of Employees 330
Plant Area 400,000
ft2
Annual Production 31,518,510
lb
Production Hrs. Annual 6,600
hrs
Location (State) Ohio

Facility Energy Cost and Usage

Source Yearly Cost Usage
Electricity Usage $618,747 11,644,548
kWh
Electricity Demand $190,232 24,692
kW-mo/yr
Electricity Fees $10,946 -
Natural Gas $674,757 92,276
MMBtu
Waste Disposal Costs
Water Usage $87,899 11,410
Tgal
Water Disposal $21,151 20,370
Tgal
TOTAL YEARLY COSTS $1,603,732
RECOMMENDED SAVINGS* $500,008 *Non-energy impacts included in savings.
IMPLEMENTED SAVINGS* $153,976

Recommendations

# Description Yearly Savings* Imp'd Cost* Status Electricity Usage Savings Electricity Demand Savings Natural Gas Savings Personnel Changes Savings Administrative Changes Savings Ancillary Material Cost Savings
01 2.6212: Turn off equipment during breaks, reduce operating time $10,825 - $10,825
108,792
kWh
- - - - -
02 2.8118: Check for accuracy of utility / power meters $9,224 - - - - - $9,224 -
03 2.7314: Reduce ventilation air $153,776 $45,000 $25,851
259,810
kWh
$2,509
-
kW-mo/yr
$125,416
-
MMBtu
- - -
04 2.7224: Reduce space conditioning during non-working hours $72,916 $709 $30,145
302,965
kWh
- $42,771
-
MMBtu
- - -
05 2.4236: Eliminate leaks in inert gas and compressed air lines/ valves $19,075 $952 $17,387
174,739
kWh
$1,688
-
kW-mo/yr
- - - -
06 2.4221: Install compressor air intakes in coolest locations $10,943 $20,000 $9,975
100,254
kWh
$968
-
kW-mo/yr
- - - -
07 2.6212: Turn off equipment during breaks, reduce operating time $27,897 - $27,897
280,377
kWh
- - - - -
08 2.7142: Utilize higher efficiency lamps and/or ballasts $115,254 $300,000 $93,516
939,859
kWh
$13,252
-
kW-mo/yr
- $6,921 - $1,565
09 2.7135: Install occupancy sensors $38,668 $14,325 $31,277
314,345
kWh
$4,432
-
kW-mo/yr
- $2,959 - -
10 2.1233: Analyze flue gas for proper air/fuel ratio $3,436 $50 - - $3,436
-
MMBtu
- - -
11 2.2414: Use waste heat from hot flue gases to preheat $37,994 $22,360 - - $37,994
-
MMBtu
- - -
TOTAL RECOMMENDED $500,008 $403,396 $246,873
2,481,141
kWh
$22,849
-
kW-mo/yr
$209,617
-
MMBtu
$9,880 $9,224 $1,565
TOTAL IMPLEMENTED $153,976 $300,000 $132,238
1,329,028
kWh
$13,252
-
kW-mo/yr
- $6,921 - $1,565
Yearly Savings* Imp'd Cost* Electricity Usage Savings Electricity Demand Savings Natural Gas Savings Personnel Changes Savings Administrative Changes Savings Ancillary Material Cost Savings
*Savings and costs are best estimates based on the center's site visit, associated engineering analysis, and typical capital and labor costs