ITAC Assessment: UD1021
ITAC logo
ITAC Assessment: UD1021
Grant Funding Opportunity NOW OPEN
Up to $300k at 50% cost share for qualifying* projects.
Grant Funding Opportunity Open
Qualifying* small and medium-sized US manufacturers, that received an ITAC, Onsite Energy/CHP TAP, or qualified equivalent assessment since 2018 can now apply for grants for implementation of assessment recommendations at up to 50% of qualifying* project costs with a maximum of $300,000 per grant.
IMPORTANT: The grant program now operates on a rolling basis and applications may be submitted at any time through the year, with quarterly reviews.
*See Full Grant Solicitation for full qualification and selection details.
Assessment Year 2020
Principal Product Car Seats and Strollers
NAICS 336991: Motorcycle, Bicycle, and Parts Manufacturing
SIC 3944: Games, Toys, and Children's Vehicles, Except Dolls and Bicycles
Sales Range $100
M
to 500
M
# of Employees 350
Plant Area 360,000
ft2
Annual Production 12,872,000
units
Production Hrs. Annual 4,420
hrs
Location (State) Ohio

Facility Energy Cost and Usage

Source Yearly Cost Usage
Electricity Usage $518,773 11,384,100
kWh
Electricity Demand $346,041 22,841
kW-mo/yr
Electricity Fees $504 -
Natural Gas $22,145 3,595
MMBtu
Waste Disposal Costs
Water Usage $21,043 2,008
Tgal
Water Disposal $20,701 2,008
Tgal
TOTAL YEARLY COSTS $929,207
RECOMMENDED SAVINGS* $129,327 *Non-energy impacts included in savings.
IMPLEMENTED SAVINGS* $103,617

Recommendations

# Description Yearly Savings* Imp'd Cost* Status Electricity Usage Savings Electricity Demand Savings Water Disposal Savings Personnel Changes Savings
01 2.6212: Turn off equipment during breaks, reduce operating time $10,283 - $6,492
142,472
kWh
$3,791
-
kW-mo/yr
- -
02 2.3132: Recharge batteries on during off-peak demand periods $32,724 - - $32,724
-
kW-mo/yr
- -
03 3.4116: Meter recycled water (to reduce sewer charges) $5,965 $1,400 - - $5,965
-
Tgal
-
04 2.4236: Eliminate leaks in inert gas and compressed air lines/ valves $8,342 - $6,474
142,057
kWh
$2,948
-
kW-mo/yr
- $(-1,080.0)
05 2.4231: Reduce the pressure of compressed air to the minimum required $6,841 - $4,700
103,148
kWh
$2,141
-
kW-mo/yr
- -
06 2.4221: Install compressor air intakes in coolest locations $4,902 $2,000 $3,368
73,911
kWh
$1,534
-
kW-mo/yr
- -
07 2.4131: Size electric motors for peak operating efficiency $8,594 $1,590 $5,905
129,579
kWh
$2,689
-
kW-mo/yr
- -
08 2.7142: Utilize higher efficiency lamps and/or ballasts $24,419 $37,053 $12,411
272,361
kWh
$10,397
-
kW-mo/yr
- $1,611
09 2.7135: Install occupancy sensors $16,106 $2,800 $7,919
173,781
kWh
$7,148
-
kW-mo/yr
- $1,039
10 2.7142: Utilize higher efficiency lamps and/or ballasts $10,902 $7,800 $5,852
128,422
kWh
$5,330
-
kW-mo/yr
- $(-280.0)
11 2.7124: Make a practice of turning off lights when not needed $249 $240 $249
5,453
kWh
- - -
TOTAL RECOMMENDED $129,327 $52,883 $53,370
1,171,184
kWh
$68,702
-
kW-mo/yr
$5,965
-
Tgal
$1,290
TOTAL IMPLEMENTED $103,617 $41,853 $41,364
907,730
kWh
$60,683
-
kW-mo/yr
- $1,570
Yearly Savings* Imp'd Cost* Electricity Usage Savings Electricity Demand Savings Water Disposal Savings Personnel Changes Savings
*Savings and costs are best estimates based on the center's site visit, associated engineering analysis, and typical capital and labor costs