Assessment Year | 2020 |
---|---|
Principal Product | Car Seats and Strollers |
NAICS | 336991: Motorcycle, Bicycle, and Parts Manufacturing |
SIC | 3944: Games, Toys, and Children's Vehicles, Except Dolls and Bicycles |
Sales Range | $100 M to 500M |
# of Employees | 350 |
Plant Area |
360,000
ft2
|
Annual Production | 12,872,000
units
|
Production Hrs. Annual | 4,420
hrs
|
Location (State) | Ohio |
Facility Energy Cost and Usage
Source | Yearly Cost | Usage | Unit Cost | ||
---|---|---|---|---|---|
Electricity Usage | $518,773 | 11,384,100 |
kWh
|
$0.046 | |
Electricity Demand | $346,041 | 22,841 |
kW-mo/yr
|
$15.15 | |
Electricity Fees | $504 | - |
|
- | |
Natural Gas | $22,145 | 3,595 |
MMBtu
|
$6.16 | |
Waste Disposal Costs | |||||
Water Usage | $21,043 | 2,008 |
Tgal
|
$10.48 | |
Water Disposal | $20,701 | 2,008 |
Tgal
|
$10.31 | |
TOTAL YEARLY COSTS | $929,207 | ||||
RECOMMENDED SAVINGS* | $129,327 |
See individual recommendations below
*Non-energy impacts included in savings.
|
|||
IMPLEMENTED SAVINGS* | $103,617 |
Recommendations
# | Description | Yearly Savings* | Imp'd Cost* | Status | Electricity Usage Savings | Electricity Demand Savings | Water Disposal Savings | Personnel Changes Savings |
---|---|---|---|---|---|---|---|---|
01 | 2.6212: Turn off equipment during breaks, reduce operating time | $10,283 | - |
$6,492
142,472
kWh
|
$3,791
-
kW-mo/yr
|
- | - | |
02 | 2.3132: Recharge batteries on during off-peak demand periods | $32,724 | - | - |
$32,724
-
kW-mo/yr
|
- | - | |
03 | 3.4116: Meter recycled water (to reduce sewer charges) | $5,965 | $1,400 | - | - |
$5,965
-
Tgal
|
- | |
04 | 2.4236: Eliminate leaks in inert gas and compressed air lines/ valves | $8,342 | - |
$6,474
142,057
kWh
|
$2,948
-
kW-mo/yr
|
- | $(-1,080.0) | |
05 | 2.4231: Reduce the pressure of compressed air to the minimum required | $6,841 | - |
$4,700
103,148
kWh
|
$2,141
-
kW-mo/yr
|
- | - | |
06 | 2.4221: Install compressor air intakes in coolest locations | $4,902 | $2,000 |
$3,368
73,911
kWh
|
$1,534
-
kW-mo/yr
|
- | - | |
07 | 2.4131: Size electric motors for peak operating efficiency | $8,594 | $1,590 |
$5,905
129,579
kWh
|
$2,689
-
kW-mo/yr
|
- | - | |
08 | 2.7142: Utilize higher efficiency lamps and/or ballasts | $24,419 | $37,053 |
$12,411
272,361
kWh
|
$10,397
-
kW-mo/yr
|
- | $1,611 | |
09 | 2.7135: Install occupancy sensors | $16,106 | $2,800 |
$7,919
173,781
kWh
|
$7,148
-
kW-mo/yr
|
- | $1,039 | |
10 | 2.7142: Utilize higher efficiency lamps and/or ballasts | $10,902 | $7,800 |
$5,852
128,422
kWh
|
$5,330
-
kW-mo/yr
|
- | $(-280.0) | |
11 | 2.7124: Make a practice of turning off lights when not needed | $249 | $240 |
$249
5,453
kWh
|
- | - | - | |
TOTAL RECOMMENDED | $129,327 | $52,883 |
$53,370
1,171,184
kWh
|
$68,702
-
kW-mo/yr
|
$5,965
-
Tgal
|
$1,290 | ||
TOTAL IMPLEMENTED | $103,617 | $41,853 |
$41,364
907,730
kWh
|
$60,683
-
kW-mo/yr
|
- | $1,570 | ||
Yearly Savings* | Imp'd Cost* | Electricity Usage Savings | Electricity Demand Savings | Water Disposal Savings | Personnel Changes Savings |
*Savings and costs are best estimates based on the center's site visit, associated engineering analysis, and typical capital and labor costs