ITAC Assessment: UD1016
ITAC logo
ITAC Assessment: UD1016
Grant Funding Opportunity NOW OPEN
Up to $300k at 50% cost share for qualifying* projects.
Grant Funding Opportunity Open
Qualifying* small and medium-sized US manufacturers, that received an ITAC, Onsite Energy/CHP TAP, or qualified equivalent assessment since 2018 can now apply for grants for implementation of assessment recommendations at up to 50% of qualifying* project costs with a maximum of $300,000 per grant.
IMPORTANT: The grant program now operates on a rolling basis and applications may be submitted at any time through the year, with quarterly reviews.
*See Full Grant Solicitation for full qualification and selection details.
Assessment Year 2020
Principal Product Precision Machine Components
NAICS 332710: Machine Shops
SIC 3599: Industrial and Commercial Machinery and Equipment, Not Elsewhere Classified
Sales Range $5
M
to 10
M
# of Employees 42
Plant Area 500,000
ft2
Annual Production 194,673
units
Production Hrs. Annual 4,480
hrs
Location (State) Ohio

Facility Energy Cost and Usage

Source Yearly Cost Usage
Electricity Usage $51,837 1,047,212
kWh
Electricity Demand $17,773 4,860
kW-mo/yr
Electricity Fees $22,216 -
Natural Gas $20,323 3,528
MMBtu
Waste Disposal Costs
Water Usage $2,520 432
Tgal
Water Disposal $2,520 432
Tgal
TOTAL YEARLY COSTS $117,188
RECOMMENDED SAVINGS* $24,249 *Non-energy impacts included in savings.
IMPLEMENTED SAVINGS* $18,962

Recommendations

# Description Yearly Savings* Imp'd Cost* Status Electricity Usage Savings Electricity Demand Savings Natural Gas Savings Personnel Changes Savings
01 2.4111: Utilize energy-efficient belts and other improved mechanisms $85 - $60
1,207
kWh
$25
-
kW-mo/yr
- -
02 2.4231: Reduce the pressure of compressed air to the minimum required $1,918 $1,358 $1,577
31,851
kWh
$341
-
kW-mo/yr
- -
03 2.4221: Install compressor air intakes in coolest locations $433 - $308
6,218
kWh
$125
-
kW-mo/yr
- -
04 2.4231: Reduce the pressure of compressed air to the minimum required $966 - $686
13,867
kWh
$280
-
kW-mo/yr
- -
05 2.2523: Reduce infiltration to refrigerated areas; isolate hot equipment from refrigerated areas $8,764 $42,000 $4,847
97,920
kWh
$3,917
-
kW-mo/yr
- -
06 2.7231: Use radiant heater for spot heating $2,079 $7,980 $437
8,820
kWh
- $1,642
-
MMBtu
-
07 2.6221: Use most efficient equipment at it's maximum capacity and less efficient equipment only when necessary $772 $50 $673
13,603
kWh
$99
-
kW-mo/yr
- -
08 2.7142: Utilize higher efficiency lamps and/or ballasts $9,232 $18,000 $6,883
139,045
kWh
$1,362
-
kW-mo/yr
- $987
TOTAL RECOMMENDED $24,249 $69,388 $15,471
312,531
kWh
$6,149
-
kW-mo/yr
$1,642
-
MMBtu
$987
TOTAL IMPLEMENTED $18,962 $60,000 $12,416
250,832
kWh
$5,559
-
kW-mo/yr
- $987
Yearly Savings* Imp'd Cost* Electricity Usage Savings Electricity Demand Savings Natural Gas Savings Personnel Changes Savings
*Savings and costs are best estimates based on the center's site visit, associated engineering analysis, and typical capital and labor costs