Assessment Year | 1996 |
---|---|
Principal Product | Steel Joists |
NAICS |
n/a
|
SIC | 3441: Fabricated Structural Metal |
Sales Range | $10 M to 50M |
# of Employees | 150 |
Plant Area |
55,400
ft2
|
Annual Production | 13,000
ton
|
Production Hrs. Annual | 6,240
hrs
|
Location (State) | Florida |
Facility Energy Cost and Usage
Source | Yearly Cost | Usage | Unit Cost | |
---|---|---|---|---|
Electricity Usage | $56,066 | 1,128,077 |
kWh
|
$0.050 |
Electricity Demand | $23,479 | 2,580 |
kW-mo/yr
|
$9.10 |
Fuel Oil #2 | $2,621 | 403 |
MMBtu
|
$6.50 |
TOTAL YEARLY COSTS | - | |||
RECOMMENDED SAVINGS* | $24,568 |
See individual recommendations below
*Non-energy impacts included in savings.
|
||
IMPLEMENTED SAVINGS* | $3,492 |
Recommendations
# | Description | Yearly Savings* | Imp'd Cost* | Status | Electricity Usage Savings | Electricity Demand Savings | Solid Waste (non-haz) Savings |
---|---|---|---|---|---|---|---|
01 | 2.7142: Utilize higher efficiency lamps and/or ballasts | $7,918 | $5,512 |
$5,450
126,612
kWh
|
$2,468
-
kW-mo/yr
|
- | |
02 | 2.7145: Install skylights | $2,362 | $2,560 |
$2,362
34,291
kWh
|
- | - | |
03 | 2.4133: Use most efficient type of electric motors | $335 | $780 |
$239
5,569
kWh
|
$96
-
kW-mo/yr
|
- | |
04 | 2.4236: Eliminate leaks in inert gas and compressed air lines/ valves | $3,492 | $1,350 |
$3,492
50,703
kWh
|
- | - | |
05 | 2.4239: Eliminate or reduce compressed air usage | $9,421 | $2,100 |
$9,421
136,577
kWh
|
- | - | |
06 | 3.6193: Install equipment (eg compactor) to reduce disposal costs | $1,040 | $3,000 | - | - |
$1,040
-
lb
|
|
TOTAL RECOMMENDED | $24,568 | $15,302 |
$20,964
353,752
kWh
|
$2,564
-
kW-mo/yr
|
$1,040
-
lb
|
||
TOTAL IMPLEMENTED | $3,492 | $1,350 |
$3,492
50,703
kWh
|
- | - | ||
Yearly Savings* | Imp'd Cost* | Electricity Usage Savings | Electricity Demand Savings | Solid Waste (non-haz) Savings |
*Savings and costs are best estimates based on the center's site visit, associated engineering analysis, and typical capital and labor costs