| Assessment Year | 2001 |
|---|---|
| Principal Product | Pharmaceutical chemicals |
| NAICS |
n/a
|
| SIC | 2860: |
| Sales Range | $10 M to 50M |
| # of Employees | 100 |
| Plant Area |
62,000
ft2
|
| Annual Production | 20,000,000
lb
|
| Production Hrs. Annual | 8,200
hrs
|
| Location (State) | North Carolina |
Facility Energy Cost and Usage
| Source | Yearly Cost | Usage | Unit Cost | |
|---|---|---|---|---|
| Electricity Usage | $137,927 | 5,284,819 |
kWh
|
$0.026 |
| Electricity Demand | $82,629 | 9,588 |
kW-mo/yr
|
$8.62 |
| Electricity Fees | $6,885 | - |
|
- |
| Natural Gas | $1,058,490 | 205,979 |
MMBtu
|
$5.14 |
| Fuel Oil #6 | $113,114 | 20,844 |
MMBtu
|
$5.43 |
| TOTAL YEARLY COSTS | - | |||
| RECOMMENDED SAVINGS* | $151,176 |
See individual recommendations below
*Non-energy impacts included in savings.
|
||
| IMPLEMENTED SAVINGS* | $33,380 | |||
Recommendations
| # | Description | Yearly Savings* | Imp'd Cost* | Status | Electricity Usage Savings | Electricity Demand Savings | Natural Gas Savings | Water Disposal Savings | Personnel Changes Savings | Administrative Changes Savings | Ancillary Material Cost Savings |
|---|---|---|---|---|---|---|---|---|---|---|---|
| 01 | 4.212: Adopt in-house material generation | $22,148 | $70,000 |
$(-4,931.0)
(-188,909)
kWh
|
$(-2,441.0)
-
kW-mo/yr
|
- | - | - | $(-1,200.0) | $30,720 | |
| 02 | 2.1133: Adjust burners for efficient operation | $33,380 | $800 | - | - |
$33,380
-
MMBtu
|
- | - | - | - | |
| 03 | 2.2113: Repair or replace steam traps | $35,343 | $5,500 | - | - |
$43,690
-
MMBtu
|
- | $(-667.0) | - | $(-7,680.0) | |
| 04 | 2.2121: Increase amount of condensate returned | $60,106 | $92,100 | n/a | - | - |
$37,512
-
MMBtu
|
$22,594
-
Tgal
|
- | - | - |
| 05 | 2.4221: Install compressor air intakes in coolest locations | $199 | $1,000 |
$130
4,987
kWh
|
$69
-
kW-mo/yr
|
- | - | - | - | - | |
| TOTAL RECOMMENDED | $151,176 | $169,400 |
$(-4,801.0)
(-183,922)
kWh
|
$(-2,372.0)
-
kW-mo/yr
|
$114,582
-
MMBtu
|
$22,594
-
Tgal
|
$(-667.0) | $(-1,200.0) | $23,040 | ||
| TOTAL IMPLEMENTED | $33,380 | $800 | - | - |
$33,380
-
MMBtu
|
- | - | - | - | ||
*Savings and costs are best estimates based on the center's site visit, associated engineering analysis, and typical capital and labor costs