ITAC Assessment: NC0219
ITAC logo
ITAC Assessment: NC0219
Grant Funding Opportunity NOW OPEN
Up to $300k at 50% cost share for qualifying* projects.
Grant Funding Opportunity Open
Qualifying* small and medium-sized US manufacturers, that received an ITAC, Onsite Energy/CHP TAP, or qualified equivalent assessment since 2018 can now apply for grants for implementation of assessment recommendations at up to 50% of qualifying* project costs with a maximum of $300,000 per grant.
IMPORTANT: The grant program now operates on a rolling basis and applications may be submitted at any time through the year, with quarterly reviews.
*See Full Grant Solicitation for full qualification and selection details.
Assessment Year 2001
Principal Product Pharmaceutical chemicals
NAICS
n/a
SIC 2860:
Sales Range $10
M
to 50
M
# of Employees 100
Plant Area 62,000
ft2
Annual Production 20,000,000
lb
Production Hrs. Annual 8,200
hrs
Location (State) North Carolina

Facility Energy Cost and Usage

Source Yearly Cost Usage
Electricity Usage $137,927 5,284,819
kWh
Electricity Demand $82,629 9,588
kW-mo/yr
Electricity Fees $6,885 -
Natural Gas $1,058,490 205,979
MMBtu
Fuel Oil #6 $113,114 20,844
MMBtu
TOTAL YEARLY COSTS -
RECOMMENDED SAVINGS* $151,176 *Non-energy impacts included in savings.
IMPLEMENTED SAVINGS* $33,380

Recommendations

# Description Yearly Savings* Imp'd Cost* Status Electricity Usage Savings Electricity Demand Savings Natural Gas Savings Water Disposal Savings Personnel Changes Savings Administrative Changes Savings Ancillary Material Cost Savings
01 4.212: Adopt in-house material generation $22,148 $70,000 $(-4,931.0)
(-188,909)
kWh
$(-2,441.0)
-
kW-mo/yr
- - - $(-1,200.0) $30,720
02 2.1133: Adjust burners for efficient operation $33,380 $800 - - $33,380
-
MMBtu
- - - -
03 2.2113: Repair or replace steam traps $35,343 $5,500 - - $43,690
-
MMBtu
- $(-667.0) - $(-7,680.0)
04 2.2121: Increase amount of condensate returned $60,106 $92,100 n/a - - $37,512
-
MMBtu
$22,594
-
Tgal
- - -
05 2.4221: Install compressor air intakes in coolest locations $199 $1,000 $130
4,987
kWh
$69
-
kW-mo/yr
- - - - -
TOTAL RECOMMENDED $151,176 $169,400 $(-4,801.0)
(-183,922)
kWh
$(-2,372.0)
-
kW-mo/yr
$114,582
-
MMBtu
$22,594
-
Tgal
$(-667.0) $(-1,200.0) $23,040
TOTAL IMPLEMENTED $33,380 $800 - - $33,380
-
MMBtu
- - - -
*Savings and costs are best estimates based on the center's site visit, associated engineering analysis, and typical capital and labor costs