Assessment Year | 2019 |
---|---|
Principal Product | Bacon |
NAICS | 311612: Meat Processed from Carcasses |
SIC | 2013: Sausages and Other Prepared Meat Products |
Sales Range | $100 M to 500M |
# of Employees | 515 |
Plant Area |
65,000
ft2
|
Annual Production | 1,200,000,000
pieces
|
Production Hrs. Annual | 5,616
hrs
|
Location (State) | Ohio |
Facility Energy Cost and Usage
Source | Yearly Cost | Usage | Unit Cost | |
---|---|---|---|---|
Electricity Usage | $2,031,980 | 34,943,773 |
kWh
|
$0.058 |
Electricity Demand | $205,368 | 56,111 |
kW-mo/yr
|
$3.66 |
Natural Gas | $262,217 | 38,283 |
MMBtu
|
$6.85 |
TOTAL YEARLY COSTS | $2,499,565 | |||
RECOMMENDED SAVINGS* | $242,356 |
See individual recommendations below
*Non-energy impacts included in savings.
|
||
IMPLEMENTED SAVINGS* | $19,419 |
Recommendations
# | Description | Yearly Savings* | Imp'd Cost* | Status | Electricity Usage Savings | Electricity Demand Savings | Personnel Changes Savings |
---|---|---|---|---|---|---|---|
01 | 2.4151: Develop a repair/replace policy | $21,932 | - |
$19,332
332,444
kWh
|
$2,600
-
kW-mo/yr
|
- | |
02 | 2.4111: Utilize energy-efficient belts and other improved mechanisms | $924 | - |
$769
13,223
kWh
|
$155
-
kW-mo/yr
|
- | |
03 | 2.2612: Use cooling tower water instead of refrigeration | $87,749 | $5,000 |
$78,701
1,353,420
kWh
|
$9,048
-
kW-mo/yr
|
- | |
04 | 2.2696: Use excess cold process fluid for industrial cooling needs | $80,784 | $10,000 |
$74,372
1,278,960
kWh
|
$6,412
-
kW-mo/yr
|
- | |
05 | 2.2696: Use excess cold process fluid for industrial cooling needs | $4,980 | - |
$4,585
78,840
kWh
|
$395
-
kW-mo/yr
|
- | |
06 | 2.4146: Use adjustable frequency drive or multiple speed motors on existing system | $3,566 | $4,400 |
$3,566
61,320
kWh
|
- | - | |
07 | 2.4146: Use adjustable frequency drive or multiple speed motors on existing system | $3,535 | $500 |
$3,535
60,788
kWh
|
- | - | |
08 | 2.4231: Reduce the pressure of compressed air to the minimum required | $2,204 | - |
$2,204
37,907
kWh
|
- | - | |
09 | 2.4236: Eliminate leaks in inert gas and compressed air lines/ valves | $1,737 | $1,000 |
$1,848
31,784
kWh
|
$249
-
kW-mo/yr
|
$(-360.0) | |
10 | 2.4146: Use adjustable frequency drive or multiple speed motors on existing system | $22,710 | $34,800 |
$18,898
324,991
kWh
|
$3,812
-
kW-mo/yr
|
- | |
11 | 2.7142: Utilize higher efficiency lamps and/or ballasts | $12,235 | $23,550 |
$10,850
186,588
kWh
|
$935
-
kW-mo/yr
|
$450 | |
TOTAL RECOMMENDED | $242,356 | $79,250 |
$218,660
3,760,265
kWh
|
$23,606
-
kW-mo/yr
|
$90 | ||
TOTAL IMPLEMENTED | $19,419 | $23,550 |
$17,639
303,335
kWh
|
$1,330
-
kW-mo/yr
|
$450 | ||
Yearly Savings* | Imp'd Cost* | Electricity Usage Savings | Electricity Demand Savings | Personnel Changes Savings |
*Savings and costs are best estimates based on the center's site visit, associated engineering analysis, and typical capital and labor costs