ITAC Assessment: UD0999
ITAC logo
ITAC Assessment: UD0999
Grant Funding Opportunity NOW OPEN
Up to $300k at 50% cost share for qualifying* projects.
Grant Funding Opportunity Open
Qualifying* small and medium-sized US manufacturers, that received an ITAC, Onsite Energy/CHP TAP, or qualified equivalent assessment since 2018 can now apply for grants for implementation of assessment recommendations at up to 50% of qualifying* project costs with a maximum of $300,000 per grant.
IMPORTANT: The grant program now operates on a rolling basis and applications may be submitted at any time through the year, with quarterly reviews.
*See Full Grant Solicitation for full qualification and selection details.
Assessment Year 2019
Principal Product Automotive Alternators and Starter Motors
NAICS 336320: Motor Vehicle Electrical and Electronic Equipment Manufacturing
SIC 3694: Electrical Equipment for Internal Combustion Engines
Sales Range greater than $500
M
# of Employees 795
Plant Area 602,941
ft2
Annual Production 5,864,908
units
Production Hrs. Annual 7,200
hrs
Location (State) Ohio

Facility Energy Cost and Usage

Source Yearly Cost Usage
Electricity Usage $1,618,060 29,152,435
kWh
Electricity Demand $324,075 57,076
kW-mo/yr
Natural Gas $320,093 58,173
MMBtu
Waste Disposal Costs
Water Usage $47,247 7,176
Tgal
Water Disposal $58,765 7,176
Tgal
TOTAL YEARLY COSTS $2,368,240
RECOMMENDED SAVINGS* $50,026 *Non-energy impacts included in savings.
IMPLEMENTED SAVINGS* $7,453

Recommendations

# Description Yearly Savings* Imp'd Cost* Status Electricity Usage Savings Electricity Demand Savings Natural Gas Savings Water Disposal Savings
01 3.4116: Meter recycled water (to reduce sewer charges) $11,762 - - - - $11,762
-
Tgal
02 2.6212: Turn off equipment during breaks, reduce operating time $7,453 - $7,453
134,280
kWh
- - -
03 2.2511: Insulate bare equipment $6,465 $596 - - $6,465
-
MMBtu
-
04 2.2511: Insulate bare equipment $4,677 $353 $3,996
72,000
kWh
$681
-
kW-mo/yr
- -
05 2.4221: Install compressor air intakes in coolest locations $19,669 $11,170 $16,811
302,907
kWh
$2,858
-
kW-mo/yr
- -
TOTAL RECOMMENDED $50,026 $12,119 $28,260
509,187
kWh
$3,539
-
kW-mo/yr
$6,465
-
MMBtu
$11,762
-
Tgal
TOTAL IMPLEMENTED $7,453 - $7,453
134,280
kWh
- - -
*Savings and costs are best estimates based on the center's site visit, associated engineering analysis, and typical capital and labor costs