| Assessment Year | 2019 |
|---|---|
| Principal Product | Automotive Alternators and Starter Motors |
| NAICS | 336320: Motor Vehicle Electrical and Electronic Equipment Manufacturing |
| SIC | 3694: Electrical Equipment for Internal Combustion Engines |
| Sales Range | greater than $500 M |
| # of Employees | 795 |
| Plant Area |
602,941
ft2
|
| Annual Production | 5,864,908
units
|
| Production Hrs. Annual | 7,200
hrs
|
| Location (State) | Ohio |
Facility Energy Cost and Usage
| Source | Yearly Cost | Usage | Unit Cost | ||
|---|---|---|---|---|---|
| Electricity Usage | $1,618,060 | 29,152,435 |
kWh
|
$0.056 | |
| Electricity Demand | $324,075 | 57,076 |
kW-mo/yr
|
$5.68 | |
| Natural Gas | $320,093 | 58,173 |
MMBtu
|
$5.50 | |
| Waste Disposal Costs | |||||
| Water Usage | $47,247 | 7,176 |
Tgal
|
$6.58 | |
| Water Disposal | $58,765 | 7,176 |
Tgal
|
$8.19 | |
| TOTAL YEARLY COSTS | $2,368,240 | ||||
| RECOMMENDED SAVINGS* | $50,026 |
See individual recommendations below
*Non-energy impacts included in savings.
|
|||
| IMPLEMENTED SAVINGS* | $7,453 | ||||
Recommendations
| # | Description | Yearly Savings* | Imp'd Cost* | Status | Electricity Usage Savings | Electricity Demand Savings | Natural Gas Savings | Water Disposal Savings |
|---|---|---|---|---|---|---|---|---|
| 01 | 3.4116: Meter recycled water (to reduce sewer charges) | $11,762 | - | - | - | - |
$11,762
-
Tgal
|
|
| 02 | 2.6212: Turn off equipment during breaks, reduce operating time | $7,453 | - |
$7,453
134,280
kWh
|
- | - | - | |
| 03 | 2.2511: Insulate bare equipment | $6,465 | $596 | - | - |
$6,465
-
MMBtu
|
- | |
| 04 | 2.2511: Insulate bare equipment | $4,677 | $353 |
$3,996
72,000
kWh
|
$681
-
kW-mo/yr
|
- | - | |
| 05 | 2.4221: Install compressor air intakes in coolest locations | $19,669 | $11,170 |
$16,811
302,907
kWh
|
$2,858
-
kW-mo/yr
|
- | - | |
| TOTAL RECOMMENDED | $50,026 | $12,119 |
$28,260
509,187
kWh
|
$3,539
-
kW-mo/yr
|
$6,465
-
MMBtu
|
$11,762
-
Tgal
|
||
| TOTAL IMPLEMENTED | $7,453 | - |
$7,453
134,280
kWh
|
- | - | - | ||
*Savings and costs are best estimates based on the center's site visit, associated engineering analysis, and typical capital and labor costs