Assessment Year | 2019 |
---|---|
Principal Product | Automotive Disk Brake Calipers & Automotive Electronic Stability Control |
NAICS | 336340: Motor Vehicle Brake System Manufacturing |
SIC | 3714: Motor Vehicle Parts and Accessories |
Sales Range | greater than $500 M |
# of Employees | 800 |
Plant Area |
549,000
ft2
|
Annual Production | 5,100,000
units
|
Production Hrs. Annual | 8,400
hrs
|
Location (State) | Ohio |
Facility Energy Cost and Usage
Source | Yearly Cost | Usage | Unit Cost | ||
---|---|---|---|---|---|
Electricity Usage | $1,142,473 | 38,820,000 |
kWh
|
$0.029 | |
Electricity Demand | $743,578 | 72,192 |
kW-mo/yr
|
$10.30 | |
Electricity Fees | $788,155 | - |
|
- | |
Natural Gas | $136,667 | 23,527 |
MMBtu
|
$5.81 | |
Waste Disposal Costs | |||||
Water Usage | $99,589 | 16,167 |
Tgal
|
$6.16 | |
Water Disposal | $74,648 | 16,167 |
Tgal
|
$4.62 | |
TOTAL YEARLY COSTS | $2,985,109 | ||||
RECOMMENDED SAVINGS* | $307,659 |
See individual recommendations below
*Non-energy impacts included in savings.
|
|||
IMPLEMENTED SAVINGS* | $211,846 |
Recommendations
# | Description | Yearly Savings* | Imp'd Cost* | Status | Electricity Usage Savings | Electricity Demand Savings | Electricity Fees Savings | Natural Gas Savings | Personnel Changes Savings |
---|---|---|---|---|---|---|---|---|---|
01 | 2.4221: Install compressor air intakes in coolest locations | $7,447 | - |
$1,866
63,427
kWh
|
$2,722
-
kW-mo/yr
|
$2,859 | - | - | |
02 | 2.4236: Eliminate leaks in inert gas and compressed air lines/ valves | $2,125 | - |
$492
16,717
kWh
|
$246
-
kW-mo/yr
|
$259 | - | $1,128 | |
03 | 2.6212: Turn off equipment during breaks, reduce operating time | $1,446 | - |
$1,446
49,154
kWh
|
- | - | - | - | |
04 | 2.2625: Chill water to the highest temperature possible | $618 | - |
$312
10,617
kWh
|
$149
-
kW-mo/yr
|
$157 | - | - | |
05 | 2.4111: Utilize energy-efficient belts and other improved mechanisms | $618 | - |
$312
10,616
kWh
|
$150
-
kW-mo/yr
|
$156 | - | - | |
06 | 2.2514: Cover open tanks | $8,047 | $1,400 | - | - | - |
$8,047
-
MMBtu
|
- | |
07 | 2.2622: Replace existing chiller with high efficiency model | $18,128 | $3,500 | - | - | - |
$18,128
-
MMBtu
|
- | |
08 | 2.3212: Optimize plant power factor | $127,402 | $60,000 | - |
$62,084
-
kW-mo/yr
|
$65,318 | - | - | |
09 | 2.2492: Use "heat wheel" or other heat exchanger to cross-exchange building exhaust air with make-up air | $48,531 | $11,000 |
$23,829
809,681
kWh
|
$12,692
-
kW-mo/yr
|
$12,010 | - | - | |
10 | 2.7313: Recycle air for heating, ventilation and air conditioning | $37,159 | $98,800 | - | - | - |
$37,159
-
MMBtu
|
- | |
11 | 2.4322: Use or replace with energy efficient substitutes | $28,290 | $5,250 |
$6,494
220,647
kWh
|
$3,113
-
kW-mo/yr
|
$3,274 |
$15,409
-
MMBtu
|
- | |
12 | 2.7142: Utilize higher efficiency lamps and/or ballasts | $27,848 | $80,000 |
$13,100
445,133
kWh
|
$6,550
-
kW-mo/yr
|
$6,888 | - | $1,310 | |
TOTAL RECOMMENDED | $307,659 | $259,950 |
$47,851
1,625,992
kWh
|
$87,706
-
kW-mo/yr
|
$90,921 |
$78,743
-
MMBtu
|
$2,438 | ||
TOTAL IMPLEMENTED | $211,846 | $151,000 |
$39,107
1,328,857
kWh
|
$84,198
-
kW-mo/yr
|
$87,231 | - | $1,310 | ||
Yearly Savings* | Imp'd Cost* | Electricity Usage Savings | Electricity Demand Savings | Electricity Fees Savings | Natural Gas Savings | Personnel Changes Savings |
*Savings and costs are best estimates based on the center's site visit, associated engineering analysis, and typical capital and labor costs