ITAC Assessment: BD0261
ITAC logo
ITAC Assessment: BD0261
Grant Funding Opportunity NOW OPEN
Up to $300k at 50% cost share for qualifying* projects.
Grant Funding Opportunity Open
Qualifying* small and medium-sized US manufacturers, that received an ITAC, Onsite Energy/CHP TAP, or qualified equivalent assessment since 2018 can now apply for grants for implementation of assessment recommendations at up to 50% of qualifying* project costs with a maximum of $300,000 per grant.
IMPORTANT: The grant program now operates on a rolling basis and applications may be submitted at any time through the year, with quarterly reviews.
*See Full Grant Solicitation for full qualification and selection details.
Assessment Year 2004
Principal Product Machined Metal and Plastic Products
NAICS 332721: Precision Turned Product Manufacturing
SIC 3451: Screw Machine Products
Sales Range $5
M
to 10
M
# of Employees 70
Plant Area 20,000
ft2
Annual Production 6,000,000
pieces
Production Hrs. Annual 5,200
hrs
Location (State) Illinois

Facility Energy Cost and Usage

Source Yearly Cost Usage
Electricity Usage $25,222 441,840
kWh
Electricity Demand $17,829 1,968
kW-mo/yr
Natural Gas $8,314 1,437
MMBtu
TOTAL YEARLY COSTS -
RECOMMENDED SAVINGS* $136,812 *Non-energy impacts included in savings.
IMPLEMENTED SAVINGS* $133,952

Recommendations

# Description Yearly Savings* Imp'd Cost* Status Electricity Usage Savings Electricity Demand Savings Natural Gas Savings Water Disposal Savings Other Liquid (non-haz) Savings Other Liquid (haz) Savings Solid Waste (non-haz) Savings Personnel Changes Savings Primary Raw Material Savings Ancillary Material Cost Savings One-time Revenue or Avoided Cost Savings Increase in Production Savings
01 2.7134: Use photocell controls $2,004 $1,500 $1,123
19,691
kWh
$730
-
kW-mo/yr
- - - - - $80 $71 - - -
02 2.4236: Eliminate leaks in inert gas and compressed air lines/ valves $2,039 $400 $1,371
24,000
kWh
$668
-
kW-mo/yr
- - - - - - - - - -
03 2.7142: Utilize higher efficiency lamps and/or ballasts $1,102 $3 $590
10,327
kWh
$180
-
kW-mo/yr
- - - - - $142 $190 - - -
04 2.7134: Use photocell controls $857 $975 $275
4,813
kWh
$244
-
kW-mo/yr
- - - - - $144 $194 - - -
05 2.2437: Recover waste heat from equipment $586 $150 - - $586
-
MMBtu
- - - - - - - - -
06 2.4231: Reduce the pressure of compressed air to the minimum required $475 - $319
5,586
kWh
$156
-
kW-mo/yr
- - - - - - - - - -
07 2.7142: Utilize higher efficiency lamps and/or ballasts $921 $722 $475
8,322
kWh
$103
-
kW-mo/yr
- - - - - $144 $199 - - -
08 2.7142: Utilize higher efficiency lamps and/or ballasts $199 $117 $38
674
kWh
$70
-
kW-mo/yr
- - - - - $42 $49 - - -
09 2.4221: Install compressor air intakes in coolest locations $159 $300 $107
1,868
kWh
$52
-
kW-mo/yr
- - - - - - - - - -
10 4.131: Modify process to reduce material use/cost $20,632 $400 - - - - - - - - - $(-2,288.0) $22,920 -
11 3.3131: Use evaporation to concentrate material $1,331 $2 - - - - - $1,331
-
gal
- - - - - -
12 3.5248: Separate and recycle scrap metal to foundry or for sale $1,000 $240 - - - - - - $1,000
-
lb
- - - - -
13 3.5315: Lease / purchase baler; sell cardboard to recycler $847 $102 - - - - - - $847
-
lb
- - - - -
14 3.4151: Minimize water usage $702 $1,035 - - - $702
-
Tgal
- - - - - - - -
15 4.443: Install automatic boiler fuel feed system $49,566 $91,500 - - - - - - - $(-31,434.0) - - - $81,000
16 4.132: Purchase new equipment to reduce material use / cost $54,392 $210,000 $(-7,643.0)
(-133,861)
kWh
- - - $(-833.0)
-
gal
- - $62,868 - - - -
TOTAL RECOMMENDED $136,812 $307,446 $(-3,345.0)
(-58,580)
kWh
$2,203
-
kW-mo/yr
$586
-
MMBtu
$702
-
Tgal
$(-833.0)
-
gal
$1,331
-
gal
$1,847
-
lb
$31,986 $703 $(-2,288.0) $22,920 $81,000
TOTAL IMPLEMENTED $133,952 $305,316 $(-4,248.0)
(-74,394)
kWh
$1,709
-
kW-mo/yr
$586
-
MMBtu
- $(-833.0)
-
gal
$1,331
-
gal
$1,847
-
lb
$31,658 $270 $(-2,288.0) $22,920 $81,000
Yearly Savings* Imp'd Cost* Electricity Usage Savings Electricity Demand Savings Natural Gas Savings Water Disposal Savings Other Liquid (non-haz) Savings Other Liquid (haz) Savings Solid Waste (non-haz) Savings Personnel Changes Savings Primary Raw Material Savings Ancillary Material Cost Savings One-time Revenue or Avoided Cost Savings Increase in Production Savings
*Savings and costs are best estimates based on the center's site visit, associated engineering analysis, and typical capital and labor costs