Assessment Year | 2019 |
---|---|
Principal Product | Cheese |
NAICS | 311513: Cheese Manufacturing |
SIC | 2022: Natural, Processed, and Imitation Cheese |
Sales Range | $10 M to 50M |
# of Employees | 43 |
Plant Area |
75,000
ft2
|
Annual Production | 14,000,000
lb
|
Production Hrs. Annual | 6,000
hrs
|
Location (State) | Ohio |
Facility Energy Cost and Usage
Source | Yearly Cost | Usage | Unit Cost | |
---|---|---|---|---|
Electricity Usage | $535,740 | 6,646,900 |
kWh
|
$0.081 |
Electricity Demand | $82,889 | 18,024 |
kW-mo/yr
|
$4.60 |
Electricity Fees | $10,982 | - |
|
- |
Natural Gas | $186,689 | 32,907 |
MMBtu
|
$5.67 |
TOTAL YEARLY COSTS | $816,300 | |||
RECOMMENDED SAVINGS* | $170,652 |
See individual recommendations below
*Non-energy impacts included in savings.
|
||
IMPLEMENTED SAVINGS* | $20,916 |
Recommendations
# | Description | Yearly Savings* | Imp'd Cost* | Status | Electricity Usage Savings | Electricity Demand Savings | Natural Gas Savings | Personnel Changes Savings |
---|---|---|---|---|---|---|---|---|
01 | 2.7261: Install timers and/or thermostats | $3,767 | - |
$3,487
43,267
kWh
|
$280
-
kW-mo/yr
|
- | - | |
02 | 2.4146: Use adjustable frequency drive or multiple speed motors on existing system | $2,443 | $1,500 |
$2,443
30,311
kWh
|
- | - | - | |
03 | 2.2113: Repair or replace steam traps | $5,974 | $1,800 | - | - |
$5,974
-
MMBtu
|
- | |
04 | 2.3212: Optimize plant power factor | $1,159 | $3,500 | - |
$1,159
-
kW-mo/yr
|
- | - | |
05 | 2.2444: Use hot process fluids to preheat incoming process fluids | $110,256 | $150,000 |
$44,930
557,440
kWh
|
$5,273
-
kW-mo/yr
|
$60,053
-
MMBtu
|
- | |
06 | 2.2625: Chill water to the highest temperature possible | $35,713 | $75,000 |
$15,284
189,633
kWh
|
- |
$20,429
-
MMBtu
|
- | |
07 | 2.2136: Install / repair insulation on steam lines | $5,847 | $11,694 | - | - |
$5,847
-
MMBtu
|
- | |
08 | 2.6212: Turn off equipment during breaks, reduce operating time | $606 | - |
$606
7,520
kWh
|
- | - | - | |
09 | 2.7142: Utilize higher efficiency lamps and/or ballasts | $4,887 | $17,856 |
$5,151
63,913
kWh
|
$414
-
kW-mo/yr
|
- | $(-678.0) | |
TOTAL RECOMMENDED | $170,652 | $261,350 |
$71,901
892,084
kWh
|
$7,126
-
kW-mo/yr
|
$92,303
-
MMBtu
|
$(-678.0) | ||
TOTAL IMPLEMENTED | $20,916 | $36,350 |
$8,200
101,744
kWh
|
$1,573
-
kW-mo/yr
|
$11,821
-
MMBtu
|
$(-678.0) | ||
Yearly Savings* | Imp'd Cost* | Electricity Usage Savings | Electricity Demand Savings | Natural Gas Savings | Personnel Changes Savings |
*Savings and costs are best estimates based on the center's site visit, associated engineering analysis, and typical capital and labor costs