| Assessment Year | 2017 |
|---|---|
| Principal Product | Decorative exhaust, shims, gaskets |
| NAICS | 336370: Motor Vehicle Metal Stamping |
| SIC | 3465: Automotive Stampings |
| Sales Range | $10 M to 50M |
| # of Employees | 180 |
| Plant Area |
154,039
ft2
|
| Annual Production | 2,574,244
units
|
| Production Hrs. Annual | 6,000
hrs
|
| Location (State) | Ohio |
Facility Energy Cost and Usage
| Source | Yearly Cost | Usage | Unit Cost | ||
|---|---|---|---|---|---|
| Electricity Usage | $150,712 | 3,154,880 |
kWh
|
$0.048 | |
| Natural Gas | $36,042 | 7,857 |
MMBtu
|
$4.59 | |
| Waste Disposal Costs | |||||
| Water Usage | $10,646 | 700 |
Tgal
|
$15.21 | |
| TOTAL YEARLY COSTS | $197,400 | ||||
| RECOMMENDED SAVINGS* | $60,302 |
See individual recommendations below
*Non-energy impacts included in savings.
|
|||
| IMPLEMENTED SAVINGS* | - | ||||
Recommendations
| # | Description | Yearly Savings* | Imp'd Cost* | Status | Electricity Usage Savings | Electricity Fees Savings | Natural Gas Savings | Primary Raw Material Savings | Ancillary Material Cost Savings |
|---|---|---|---|---|---|---|---|---|---|
| 01 | 2.3212: Optimize plant power factor | $2,704 | $1,000 | - | $2,704 | - | - | - | |
| 02 | 3.6193: Install equipment (eg compactor) to reduce disposal costs | $11,604 | $10,000 | - | - | - | $11,604 | - | |
| 03 | 2.7314: Reduce ventilation air | $2,584 | $3,000 | - | - |
$2,584
-
MMBtu
|
- | - | |
| 04 | 2.7224: Reduce space conditioning during non-working hours | $471 | - |
$86
1,792
kWh
|
- |
$385
-
MMBtu
|
- | - | |
| 05 | 2.4224: Upgrade controls on compressors | $8,352 | $21,000 |
$8,352
174,000
kWh
|
- | - | - | - | |
| 06 | 2.4231: Reduce the pressure of compressed air to the minimum required | $1,239 | $30 |
$1,239
25,818
kWh
|
- | - | - | - | |
| 07 | 2.4221: Install compressor air intakes in coolest locations | $1,559 | $2,000 |
$1,559
32,484
kWh
|
- | - | - | - | |
| 08 | 2.4239: Eliminate or reduce compressed air usage | $10,903 | $1,500 |
$10,903
227,145
kWh
|
- | - | - | - | |
| 09 | 2.4113: Install motor voltage controller on lightly loaded motors | $3,345 | $10,950 |
$3,345
69,693
kWh
|
- | - | - | - | |
| 10 | 2.4111: Utilize energy-efficient belts and other improved mechanisms | $1,649 | - |
$1,649
34,363
kWh
|
- | - | - | - | |
| 11 | 2.6212: Turn off equipment during breaks, reduce operating time | $1,012 | - |
$1,012
21,075
kWh
|
- | - | - | - | |
| 12 | 2.7142: Utilize higher efficiency lamps and/or ballasts | $13,115 | $31,736 |
$10,273
214,018
kWh
|
- | - | - | $2,842 | |
| 13 | 2.7135: Install occupancy sensors | $992 | $1,230 |
$852
17,741
kWh
|
- | - | - | $140 | |
| 14 | 2.7131: Add area lighting switches | $671 | $180 |
$584
12,165
kWh
|
- | - | - | $87 | |
| 15 | 2.2511: Insulate bare equipment | $102 | $420 |
$102
2,125
kWh
|
- | - | - | - | |
| TOTAL RECOMMENDED | $60,302 | $83,046 |
$39,956
832,419
kWh
|
$2,704 |
$2,969
-
MMBtu
|
$11,604 | $3,069 | ||
| TOTAL IMPLEMENTED | - | - | - | - | - | - | - | ||
| Yearly Savings* | Imp'd Cost* | Electricity Usage Savings | Electricity Fees Savings | Natural Gas Savings | Primary Raw Material Savings | Ancillary Material Cost Savings | |||
*Savings and costs are best estimates based on the center's site visit, associated engineering analysis, and typical capital and labor costs