Assessment Year | 2009 |
---|---|
Principal Product | Aluminum door/windor frame |
NAICS | 331313: Alumina Refining and Primary Aluminum Production |
SIC | 3334: Primary Production of Aluminum |
Sales Range | $10 M to 50M |
# of Employees | 60 |
Plant Area |
125,000
ft2
|
Annual Production | 7,000,000
lb
|
Production Hrs. Annual | 4,250
hrs
|
Location (State) | Missouri |
Facility Energy Cost and Usage
Source | Yearly Cost | Usage | Unit Cost | |
---|---|---|---|---|
Electricity Usage | $162,606 | 2,647,200 |
kWh
|
$0.061 |
Natural Gas | $222,163 | 20,560 |
MMBtu
|
$10.81 |
TOTAL YEARLY COSTS | - | |||
RECOMMENDED SAVINGS* | $61,288 |
See individual recommendations below
*Non-energy impacts included in savings.
|
||
IMPLEMENTED SAVINGS* | $31,751 |
Recommendations
# | Description | Yearly Savings* | Imp'd Cost* | Status | Electricity Usage Savings | Natural Gas Savings |
---|---|---|---|---|---|---|
01 | 2.7142: Utilize higher efficiency lamps and/or ballasts | $14,991 | $38,600 |
$14,991
225,403
kWh
|
- | |
02 | 2.7142: Utilize higher efficiency lamps and/or ballasts | $1,160 | $5,600 |
$1,160
16,140
kWh
|
- | |
03 | 2.7135: Install occupancy sensors | $802 | $460 |
$802
13,062
kWh
|
- | |
04 | 2.4236: Eliminate leaks in inert gas and compressed air lines/ valves | $15,600 | $850 |
$15,600
234,110
kWh
|
- | |
05 | 2.4231: Reduce the pressure of compressed air to the minimum required | $2,268 | - |
$2,268
36,945
kWh
|
- | |
06 | 2.2437: Recover waste heat from equipment | $15,312 | $10,000 | - |
$15,312
-
MMBtu
|
|
07 | 2.2437: Recover waste heat from equipment | $11,155 | $10,000 | - |
$11,155
-
MMBtu
|
|
TOTAL RECOMMENDED | $61,288 | $65,510 |
$34,821
525,660
kWh
|
$26,467
-
MMBtu
|
||
TOTAL IMPLEMENTED | $31,751 | $45,050 |
$31,751
475,653
kWh
|
- | ||
Yearly Savings* | Imp'd Cost* | Electricity Usage Savings | Natural Gas Savings |
*Savings and costs are best estimates based on the center's site visit, associated engineering analysis, and typical capital and labor costs