Assessment Year | 2016 |
---|---|
Principal Product | All Other Plastics Product Manufacturing |
NAICS | 326199: All Other Plastics Product Manufacturing |
SIC | 3089: Plastics Products, Not Elsewhere Classified |
Sales Range | $10 M to 50M |
# of Employees | 110 |
Plant Area |
206,800
ft2
|
Annual Production | 14,000,000
lb
|
Production Hrs. Annual | 6,048
hrs
|
Location (State) | Ohio |
Facility Energy Cost and Usage
Source | Yearly Cost | Usage | Unit Cost | ||
---|---|---|---|---|---|
Electricity Usage | $459,142 | 6,253,387 |
kWh
|
$0.073 | |
Electricity Demand | $105,387 | 14,292 |
kW-mo/yr
|
$7.37 | |
Electricity Fees | $51,769 | - |
|
- | |
Natural Gas | $41,728 | 5,637 |
MMBtu
|
$7.40 | |
Waste Disposal Costs | |||||
Water Usage | $3,775 | 726 |
Tgal
|
$5.20 | |
Water Disposal | $3,243 | 726 |
Tgal
|
$4.47 | |
TOTAL YEARLY COSTS | $665,044 | ||||
RECOMMENDED SAVINGS* | $147,832 |
See individual recommendations below
*Non-energy impacts included in savings.
|
|||
IMPLEMENTED SAVINGS* | - |
Recommendations
# | Description | Yearly Savings* | Imp'd Cost* | Status | Electricity Usage Savings | Electricity Demand Savings | Electricity Fees Savings | Ancillary Material Cost Savings |
---|---|---|---|---|---|---|---|---|
01 | 2.8114: Change rate schedules or other changes in utility service | $89,455 | - | - | - | $89,455 | - | |
02 | 2.3212: Optimize plant power factor | $15,347 | $8,500 | - | - | $15,347 | - | |
03 | 2.2511: Insulate bare equipment | $5,795 | $690 |
$4,828
65,318
kWh
|
$967
-
kW-mo/yr
|
- | - | |
04 | 2.7135: Install occupancy sensors | $9,787 | $1,920 |
$9,244
125,077
kWh
|
- | - | $543 | |
05 | 2.7142: Utilize higher efficiency lamps and/or ballasts | $9,504 | $1,152 |
$7,415
100,329
kWh
|
$1,485
-
kW-mo/yr
|
- | $604 | |
06 | 2.7142: Utilize higher efficiency lamps and/or ballasts | $1,151 | - |
$934
12,640
kWh
|
$206
-
kW-mo/yr
|
- | $11 | |
07 | 2.4236: Eliminate leaks in inert gas and compressed air lines/ valves | $3,542 | $1,000 |
$2,951
39,929
kWh
|
$591
-
kW-mo/yr
|
- | - | |
08 | 2.4221: Install compressor air intakes in coolest locations | $2,067 | $1,500 |
$1,722
23,304
kWh
|
$345
-
kW-mo/yr
|
- | - | |
09 | 2.4231: Reduce the pressure of compressed air to the minimum required | $751 | - |
$626
8,467
kWh
|
$125
-
kW-mo/yr
|
- | - | |
10 | 2.4239: Eliminate or reduce compressed air usage | $3,078 | $6,000 |
$2,564
34,693
kWh
|
$514
-
kW-mo/yr
|
- | - | |
11 | 2.4239: Eliminate or reduce compressed air usage | $7,355 | $21,500 |
$6,128
82,917
kWh
|
$1,227
-
kW-mo/yr
|
- | - | |
TOTAL RECOMMENDED | $147,832 | $42,262 |
$36,412
492,674
kWh
|
$5,460
-
kW-mo/yr
|
$104,802 | $1,158 | ||
TOTAL IMPLEMENTED | - | - | - | - | - | - | ||
Yearly Savings* | Imp'd Cost* | Electricity Usage Savings | Electricity Demand Savings | Electricity Fees Savings | Ancillary Material Cost Savings |
*Savings and costs are best estimates based on the center's site visit, associated engineering analysis, and typical capital and labor costs