Assessment Year | 2015 |
---|---|
Principal Product | Automotive Steering Components and CVT Transmission Parts |
NAICS | 336330: Motor Vehicle Steering and Suspension Components (except Spring) Manufacturing |
SIC | 3714: Motor Vehicle Parts and Accessories |
Sales Range | $100 M to 500M |
# of Employees | 474 |
Plant Area |
286,518
ft2
|
Annual Production | 834,000
units
|
Production Hrs. Annual | 5,880
hrs
|
Location (State) | Ohio |
Facility Energy Cost and Usage
Source | Yearly Cost | Usage | Unit Cost | |
---|---|---|---|---|
Electricity Usage | $987,116 | 16,975,875 |
kWh
|
$0.058 |
Electricity Demand | $610,159 | 36,960 |
kW-mo/yr
|
$16.51 |
Natural Gas | $291,211 | 50,670 |
MMBtu
|
$5.75 |
TOTAL YEARLY COSTS | - | |||
RECOMMENDED SAVINGS* | $108,460 |
See individual recommendations below
*Non-energy impacts included in savings.
|
||
IMPLEMENTED SAVINGS* | $41,448 |
Recommendations
# | Description | Yearly Savings* | Imp'd Cost* | Status | Electricity Usage Savings | Electricity Demand Savings | Natural Gas Savings | Personnel Changes Savings |
---|---|---|---|---|---|---|---|---|
01 | 2.4111: Utilize energy-efficient belts and other improved mechanisms | $1,695 | - |
$1,092
17,895
kWh
|
$603
-
kW-mo/yr
|
- | - | |
02 | 2.4322: Use or replace with energy efficient substitutes | $22,431 | $2,260 |
$14,453
236,928
kWh
|
$7,978
-
kW-mo/yr
|
- | - | |
03 | 2.4221: Install compressor air intakes in coolest locations | $17,704 | $6,000 |
$4,195
68,771
kWh
|
$13,509
-
kW-mo/yr
|
- | - | |
04 | 2.4239: Eliminate or reduce compressed air usage | $5,661 | $825 |
$1,285
21,059
kWh
|
$4,376
-
kW-mo/yr
|
- | - | |
05 | 2.4236: Eliminate leaks in inert gas and compressed air lines/ valves | $4,521 | $1,000 |
$4,459
73,104
kWh
|
$2,462
-
kW-mo/yr
|
- | $(-2,400.0) | |
06 | 2.2426: Use waste heat from flue gases to heat space conditioning air | $39,316 | $29,746 |
$(-2,523.0)
(-41,366)
kWh
|
$(-935.0)
-
kW-mo/yr
|
$42,774
-
MMBtu
|
- | |
07 | 2.6218: Turn off equipment when not in use | $530 | $1,480 |
$530
8,695
kWh
|
- | - | - | |
08 | 2.7142: Utilize higher efficiency lamps and/or ballasts | $12,271 | $85,000 |
$8,422
138,070
kWh
|
$4,649
-
kW-mo/yr
|
- | $(-800.0) | |
09 | 2.7135: Install occupancy sensors | $4,331 | $6,300 |
$2,574
42,201
kWh
|
$1,421
-
kW-mo/yr
|
- | $336 | |
TOTAL RECOMMENDED | $108,460 | $132,611 |
$34,487
565,357
kWh
|
$34,063
-
kW-mo/yr
|
$42,774
-
MMBtu
|
$(-2,864.0) | ||
TOTAL IMPLEMENTED | $41,448 | $89,740 |
$28,956
474,692
kWh
|
$15,692
-
kW-mo/yr
|
- | $(-3,200.0) | ||
Yearly Savings* | Imp'd Cost* | Electricity Usage Savings | Electricity Demand Savings | Natural Gas Savings | Personnel Changes Savings |
*Savings and costs are best estimates based on the center's site visit, associated engineering analysis, and typical capital and labor costs