Assessment Year | 2012 |
---|---|
Principal Product | Plastic Bags |
NAICS | 326111: Plastics Bag and Pouch Manufacturing |
SIC | 2673: Plastics, Foil, and Coated Paper Bags |
Sales Range | $10 M to 50M |
# of Employees | 48 |
Plant Area |
51,000
ft2
|
Annual Production | 17,000,000
lb
|
Production Hrs. Annual | 8,736
hrs
|
Location (State) | Florida |
Facility Energy Cost and Usage
Source | Yearly Cost | Usage | Unit Cost | |
---|---|---|---|---|
Electricity Usage | $406,873 | 5,278,403 |
kWh
|
$0.077 |
Electricity Demand | $49,880 | 10,343 |
kW-mo/yr
|
$4.82 |
Electricity Fees | $39,297 | - |
|
- |
TOTAL YEARLY COSTS | - | |||
RECOMMENDED SAVINGS* | $57,520 |
See individual recommendations below
*Non-energy impacts included in savings.
|
||
IMPLEMENTED SAVINGS* | $41,246 |
Recommendations
# | Description | Yearly Savings* | Imp'd Cost* | Status | Electricity Usage Savings | Electricity Demand Savings |
---|---|---|---|---|---|---|
01 | 2.4146: Use adjustable frequency drive or multiple speed motors on existing system | $20,266 | $11,960 |
$18,660
242,341
kWh
|
$1,606
-
kW-mo/yr
|
|
02 | 2.2511: Insulate bare equipment | $14,666 | $2,135 |
$13,156
170,857
kWh
|
$1,510
-
kW-mo/yr
|
|
03 | 2.4322: Use or replace with energy efficient substitutes | $6,947 | $12,324 |
$6,076
78,907
kWh
|
$871
-
kW-mo/yr
|
|
04 | 2.4146: Use adjustable frequency drive or multiple speed motors on existing system | $5,323 | $3,480 |
$4,901
63,648
kWh
|
$422
-
kW-mo/yr
|
|
05 | 2.4236: Eliminate leaks in inert gas and compressed air lines/ valves | $3,130 | $1,660 |
$2,678
34,780
kWh
|
$452
-
kW-mo/yr
|
|
06 | 2.5121: Redesign flow to minimize mass transfer length | $996 | $2,594 |
$919
11,937
kWh
|
$77
-
kW-mo/yr
|
|
07 | 2.7135: Install occupancy sensors | $1,962 | $520 |
$1,808
23,483
kWh
|
$154
-
kW-mo/yr
|
|
08 | 2.4231: Reduce the pressure of compressed air to the minimum required | $1,668 | $80 |
$1,475
19,151
kWh
|
$193
-
kW-mo/yr
|
|
09 | 2.7145: Install skylights | $1,608 | $5,550 |
$1,354
17,597
kWh
|
$254
-
kW-mo/yr
|
|
10 | 2.7142: Utilize higher efficiency lamps and/or ballasts | $954 | $1,230 |
$877
11,392
kWh
|
$77
-
kW-mo/yr
|
|
TOTAL RECOMMENDED | $57,520 | $41,533 |
$51,904
674,093
kWh
|
$5,616
-
kW-mo/yr
|
||
TOTAL IMPLEMENTED | $41,246 | $33,848 |
$37,394
485,639
kWh
|
$3,852
-
kW-mo/yr
|
||
Yearly Savings* | Imp'd Cost* | Electricity Usage Savings | Electricity Demand Savings |
*Savings and costs are best estimates based on the center's site visit, associated engineering analysis, and typical capital and labor costs