ITAC Assessment: UD0928
ITAC logo
ITAC Assessment: UD0928
Grant Funding Opportunity NOW OPEN
Up to $300k at 50% cost share for qualifying* projects.
Grant Funding Opportunity Open
Qualifying* small and medium-sized US manufacturers, that received an ITAC, Onsite Energy/CHP TAP, or qualified equivalent assessment since 2018 can now apply for grants for implementation of assessment recommendations at up to 50% of qualifying* project costs with a maximum of $300,000 per grant.
IMPORTANT: The grant program now operates on a rolling basis and applications may be submitted at any time through the year, with quarterly reviews.
*See Full Grant Solicitation for full qualification and selection details.
Assessment Year 2015
Principal Product Titanium Mill: Flat and Billet
NAICS 332312: Fabricated Structural Metal Manufacturing
SIC 3441: Fabricated Structural Metal
Sales Range $100
M
to 500
M
# of Employees 600
Plant Area 750,000
ft2
Annual Production 17,000,000
lb
Production Hrs. Annual 8,760
hrs
Location (State) Ohio

Facility Energy Cost and Usage

Source Yearly Cost Usage
Electricity Usage $3,557,720 74,594,610
kWh
Electricity Demand $522,834 183,552
kW-mo/yr
Natural Gas $2,037,726 376,776
MMBtu
TOTAL YEARLY COSTS -
RECOMMENDED SAVINGS* $793,900 *Non-energy impacts included in savings.
IMPLEMENTED SAVINGS* -

Recommendations

# Description Yearly Savings* Imp'd Cost* Status Electricity Usage Savings Electricity Demand Savings Natural Gas Savings Administrative Changes Savings Ancillary Material Cost Savings
01 2.4111: Utilize energy-efficient belts and other improved mechanisms $10,389 - $9,740
191,123
kWh
$649
-
kW-mo/yr
- - -
02 2.7231: Use radiant heater for spot heating $153,677 $48,000 $165,658
3,250,749
kWh
$16,703
-
kW-mo/yr
$(-28,684.0)
-
MMBtu
- -
03 2.7142: Utilize higher efficiency lamps and/or ballasts $314,492 $152,750 $286,300
5,618,135
kWh
$19,086
-
kW-mo/yr
- $9,106 -
04 2.7135: Install occupancy sensors $2,735 $12,995 $2,439
47,872
kWh
- - $296 -
05 2.1233: Analyze flue gas for proper air/fuel ratio $52,184 $105,000 - - $52,184
-
MMBtu
- -
06 2.2514: Cover open tanks $2,876 $2,196 - - $2,876
-
MMBtu
- -
07 2.2414: Use waste heat from hot flue gases to preheat $154,780 $150,000 - - $154,780
-
MMBtu
- -
08 2.4113: Install motor voltage controller on lightly loaded motors $11,986 $18,300 $11,237
220,500
kWh
$749
-
kW-mo/yr
- - -
09 2.2437: Recover waste heat from equipment $12,264 $30,000 - - $12,264
-
MMBtu
- -
10 2.4222: Install adequate dryers on air lines to eliminate blowdown $5,622 $25,000 $5,271
103,444
kWh
$351
-
kW-mo/yr
- - -
11 2.4236: Eliminate leaks in inert gas and compressed air lines/ valves $4,007 $1,000 $8,257
162,021
kWh
$550
-
kW-mo/yr
- $(-4,800.0) -
12 3.3111: Adjust ph for neutralization $68,888 $34,000 $(-92.0)
(-1,800)
kWh
- - $(-1,200.0) $70,180
TOTAL RECOMMENDED $793,900 $579,241 $488,810
9,592,044
kWh
$38,088
-
kW-mo/yr
$193,420
-
MMBtu
$3,402 $70,180
TOTAL IMPLEMENTED - - - - - - -
Yearly Savings* Imp'd Cost* Electricity Usage Savings Electricity Demand Savings Natural Gas Savings Administrative Changes Savings Ancillary Material Cost Savings
*Savings and costs are best estimates based on the center's site visit, associated engineering analysis, and typical capital and labor costs