Assessment Year | 2015 |
---|---|
Principal Product | Cleaning Chemicals |
NAICS | 325611: Soap and Other Detergent Manufacturing |
SIC | 2841: Soap and Other Detergents, Except Specialty Cleaners |
Sales Range | $50 M to 100M |
# of Employees | 85 |
Plant Area |
200,000
ft2
|
Annual Production | 99,372,260
lb
|
Production Hrs. Annual | 6,240
hrs
|
Location (State) | Ohio |
Facility Energy Cost and Usage
Source | Yearly Cost | Usage | Unit Cost | |
---|---|---|---|---|
Electricity Usage | $172,656 | 2,233,120 |
kWh
|
$0.077 |
Electricity Demand | $21,582 | 4,776 |
kW-mo/yr
|
$4.52 |
Natural Gas | $95,608 | 16,125 |
MMBtu
|
$5.93 |
TOTAL YEARLY COSTS | - | |||
RECOMMENDED SAVINGS* | $36,805 |
See individual recommendations below
*Non-energy impacts included in savings.
|
||
IMPLEMENTED SAVINGS* | $23,211 |
Recommendations
# | Description | Yearly Savings* | Imp'd Cost* | Status | Electricity Usage Savings | Electricity Demand Savings | Natural Gas Savings | Water Disposal Savings | Personnel Changes Savings | Water Consumption Savings |
---|---|---|---|---|---|---|---|---|---|---|
01 | 2.7314: Reduce ventilation air | $16,159 | - | - | - |
$16,159
-
MMBtu
|
- | - | - | |
02 | 2.4111: Utilize energy-efficient belts and other improved mechanisms | $405 | - |
$364
5,105
kWh
|
$41
-
kW-mo/yr
|
- | - | - | - | |
03 | 2.1233: Analyze flue gas for proper air/fuel ratio | $723 | - | - | - |
$723
-
MMBtu
|
- | - | - | |
04 | 2.2122: Install / repair insulation on condensate lines | $381 | $275 | - | - |
$381
-
MMBtu
|
- | - | - | |
05 | 2.4236: Eliminate leaks in inert gas and compressed air lines/ valves | $2,887 | $950 |
$2,596
36,395
kWh
|
$291
-
kW-mo/yr
|
- | - | - | - | |
06 | 2.2437: Recover waste heat from equipment | $1,838 | $1,250 | - | - |
$1,838
-
MMBtu
|
- | - | - | |
07 | 2.4221: Install compressor air intakes in coolest locations | $1,470 | $1,000 |
$1,361
19,082
kWh
|
$109
-
kW-mo/yr
|
- | - | - | - | |
08 | 2.6212: Turn off equipment during breaks, reduce operating time | $1,618 | $700 |
$1,618
22,690
kWh
|
- | - | - | - | - | |
09 | 2.4146: Use adjustable frequency drive or multiple speed motors on existing system | $1,190 | $4,300 |
$1,190
16,682
kWh
|
- | - | - | - | - | |
10 | 2.2511: Insulate bare equipment | $3,379 | $8,000 |
$2,907
40,763
kWh
|
$326
-
kW-mo/yr
|
- | - | $146 | - | |
11 | 2.7121: Utilize daylight whenever possible in lieu of artificial light | $2,030 | $6,052 |
$2,030
28,462
kWh
|
- | - | - | - | - | |
12 | 3.4133: Clean fouling from water lines regularly | $4,725 | $11,000 |
$(-30.0)
(-425)
kWh
|
$(-145.0)
-
kW-mo/yr
|
- |
$2,450
-
Tgal
|
- |
$2,450
-
Tgal
|
|
TOTAL RECOMMENDED | $36,805 | $33,527 |
$12,036
168,754
kWh
|
$622
-
kW-mo/yr
|
$19,101
-
MMBtu
|
$2,450
-
Tgal
|
$146 |
$2,450
-
Tgal
|
||
TOTAL IMPLEMENTED | $23,211 | $9,225 |
$5,867
82,263
kWh
|
$658
-
kW-mo/yr
|
$16,540
-
MMBtu
|
- | $146 | - | ||
Yearly Savings* | Imp'd Cost* | Electricity Usage Savings | Electricity Demand Savings | Natural Gas Savings | Water Disposal Savings | Personnel Changes Savings | Water Consumption Savings |
*Savings and costs are best estimates based on the center's site visit, associated engineering analysis, and typical capital and labor costs