Assessment Year | 2014 |
---|---|
Principal Product | Quartz Tube |
NAICS | 327120: Clay Building Material and Refractories Manufacturing |
SIC | 3297: Nonclay Refractories |
Sales Range | $10 M to 50M |
# of Employees | 50 |
Plant Area |
311,472
ft2
|
Annual Production | 385,809
lb
|
Production Hrs. Annual | 8,760
hrs
|
Location (State) | Ohio |
Facility Energy Cost and Usage
Source | Yearly Cost | Usage | Unit Cost | |
---|---|---|---|---|
Electricity Usage | $1,158,990 | 21,815,727 |
kWh
|
$0.053 |
Electricity Demand | $138,874 | 39,504 |
kW-mo/yr
|
$3.52 |
Natural Gas | $578,072 | 97,823 |
MMBtu
|
$5.91 |
TOTAL YEARLY COSTS | - | |||
RECOMMENDED SAVINGS* | $70,740 |
See individual recommendations below
*Non-energy impacts included in savings.
|
||
IMPLEMENTED SAVINGS* | $18,187 |
Recommendations
# | Description | Yearly Savings* | Imp'd Cost* | Status | Electricity Usage Savings | Electricity Demand Savings | Electricity Fees Savings | Natural Gas Savings | Water Disposal Savings |
---|---|---|---|---|---|---|---|---|---|
01 | 2.7224: Reduce space conditioning during non-working hours | $20,106 | $510 | - | - | - |
$20,106
-
MMBtu
|
- | |
02 | 2.7121: Utilize daylight whenever possible in lieu of artificial light | $1,680 | $1,125 |
$1,680
32,346
kWh
|
- | - | - | - | |
03 | 2.7135: Install occupancy sensors | $16,710 | $4,000 |
$13,089
251,754
kWh
|
$1,217
-
kW-mo/yr
|
$2,404 | - | - | |
04 | 2.7144: Install spectral reflectors / delamp | $759 | $500 |
$513
9,867
kWh
|
$48
-
kW-mo/yr
|
$198 | - | - | |
05 | 2.7142: Utilize higher efficiency lamps and/or ballasts | $667 | $2,940 |
$530
10,197
kWh
|
$49
-
kW-mo/yr
|
$88 | - | - | |
06 | 3.4116: Meter recycled water (to reduce sewer charges) | $11,214 | $5,000 | - | - | - | - |
$11,214
-
Tgal
|
|
07 | 2.4236: Eliminate leaks in inert gas and compressed air lines/ valves | $3,032 | $1,000 |
$3,049
58,621
kWh
|
$283
-
kW-mo/yr
|
$(-300.0) | - | - | |
08 | 2.4221: Install compressor air intakes in coolest locations | $1,327 | $3,000 |
$1,214
23,358
kWh
|
$113
-
kW-mo/yr
|
- | - | - | |
09 | 2.4231: Reduce the pressure of compressed air to the minimum required | $797 | - |
$729
14,016
kWh
|
$68
-
kW-mo/yr
|
- | - | - | |
10 | 2.4231: Reduce the pressure of compressed air to the minimum required | $797 | - |
$729
14,016
kWh
|
$68
-
kW-mo/yr
|
- | - | - | |
11 | 2.4113: Install motor voltage controller on lightly loaded motors | $7,664 | $8,319 |
$7,014
134,901
kWh
|
$650
-
kW-mo/yr
|
- | - | - | |
12 | 2.2414: Use waste heat from hot flue gases to preheat | $5,987 | $17,000 | - | - | - |
$5,987
-
MMBtu
|
- | |
TOTAL RECOMMENDED | $70,740 | $43,394 |
$28,547
549,076
kWh
|
$2,496
-
kW-mo/yr
|
$2,390 |
$26,093
-
MMBtu
|
$11,214
-
Tgal
|
||
TOTAL IMPLEMENTED | $18,187 | $10,065 |
$6,717
129,196
kWh
|
$468
-
kW-mo/yr
|
$(-212.0) | - |
$11,214
-
Tgal
|
||
Yearly Savings* | Imp'd Cost* | Electricity Usage Savings | Electricity Demand Savings | Electricity Fees Savings | Natural Gas Savings | Water Disposal Savings |
*Savings and costs are best estimates based on the center's site visit, associated engineering analysis, and typical capital and labor costs