ITAC Assessment: MS0067
ITAC logo
ITAC Assessment: MS0067
Grant Funding Opportunity NOW OPEN
Up to $300k at 50% cost share for qualifying* projects.
Grant Funding Opportunity Open
Qualifying* small and medium-sized US manufacturers, that received an ITAC, Onsite Energy/CHP TAP, or qualified equivalent assessment since 2018 can now apply for grants for implementation of assessment recommendations at up to 50% of qualifying* project costs with a maximum of $300,000 per grant.
IMPORTANT: The grant program now operates on a rolling basis and applications may be submitted at any time through the year, with quarterly reviews.
*See Full Grant Solicitation for full qualification and selection details.
Assessment Year 1996
Principal Product Tempered and Decorative Glass
NAICS
n/a
SIC 3231: Glass Products, Made of Purchased Glass
Sales Range $5
M
to 10
M
# of Employees 65
Plant Area 175,000
ft2
Annual Production 3,432
thousand feet
Production Hrs. Annual 4,160
hrs
Location (State) Alabama

Facility Energy Cost and Usage

Source Yearly Cost Usage
Electricity Usage $60,409 3,179,953
kWh
Electricity Demand $58,994 12,026
kW-mo/yr
LPG $6,201 743
MMBtu
TOTAL YEARLY COSTS -
RECOMMENDED SAVINGS* $16,941 *Non-energy impacts included in savings.
IMPLEMENTED SAVINGS* $7,900

Recommendations

# Description Yearly Savings* Imp'd Cost* Status Electricity Usage Savings Electricity Demand Savings Electricity Fees Savings Administrative Changes Savings
01 2.7122: Disconnect ballasts $5,027 $9,976 $1,372
128,664
kWh
$1,803
-
kW-mo/yr
$1,852 -
02 2.4314: Use synthetic lubricant $389 $50 $106
9,965
kWh
$140
-
kW-mo/yr
$143 -
03 2.7131: Add area lighting switches $3,625 $786 $1,124
105,510
kWh
$983
-
kW-mo/yr
$1,518 -
04 3.5315: Lease / purchase baler; sell cardboard to recycler $7,900 $6,500 - - - $7,900
TOTAL RECOMMENDED $16,941 $17,312 $2,602
244,139
kWh
$2,926
-
kW-mo/yr
$3,513 $7,900
TOTAL IMPLEMENTED $7,900 $6,500 - - - $7,900
*Savings and costs are best estimates based on the center's site visit, associated engineering analysis, and typical capital and labor costs