| Assessment Year | 2014 |
|---|---|
| Principal Product | PV Modules |
| NAICS | 334413: Semiconductor and Related Device Manufacturing |
| SIC | 3674: Semiconductors and Related Devices |
| Sales Range | $100 M to 500M |
| # of Employees | 1,100 |
| Plant Area |
540,000
ft2
|
| Annual Production | 2,000,000
pieces
|
| Production Hrs. Annual | 8,712
hrs
|
| Location (State) | Ohio |
Facility Energy Cost and Usage
| Source | Yearly Cost | Usage | Unit Cost | |
|---|---|---|---|---|
| Electricity Usage | $2,265,856 | 67,315,973 |
kWh
|
$0.034 |
| Electricity Demand | $94,332 | 10,014 |
kW-mo/yr
|
$9.42 |
| Natural Gas | $67,992 | 8,499 |
MMBtu
|
$8.00 |
| TOTAL YEARLY COSTS | - | |||
| RECOMMENDED SAVINGS* | $76,923 |
See individual recommendations below
*Non-energy impacts included in savings.
|
||
| IMPLEMENTED SAVINGS* | $62,557 | |||
Recommendations
| # | Description | Yearly Savings* | Imp'd Cost* | Status | Electricity Usage Savings | Electricity Demand Savings | Natural Gas Savings | Personnel Changes Savings |
|---|---|---|---|---|---|---|---|---|
| 01 | 2.2623: Minimize condenser cooling water temperature | $13,929 | - |
$8,334
247,588
kWh
|
$5,595
-
kW-mo/yr
|
- | - | |
| 02 | 2.2211: Use optimum temperature | $5,296 | - | - | - |
$5,296
-
MMBtu
|
- | |
| 03 | 2.4221: Install compressor air intakes in coolest locations | $3,682 | - |
$2,662
79,071
kWh
|
$1,020
-
kW-mo/yr
|
- | - | |
| 04 | 2.4111: Utilize energy-efficient belts and other improved mechanisms | $3,046 | - |
$2,202
65,424
kWh
|
$844
-
kW-mo/yr
|
- | - | |
| 05 | 2.7142: Utilize higher efficiency lamps and/or ballasts | $50,533 | $188,160 |
$33,667
1,000,182
kWh
|
$12,906
-
kW-mo/yr
|
- | $3,960 | |
| 06 | 2.4113: Install motor voltage controller on lightly loaded motors | $437 | $2,350 |
$316
9,385
kWh
|
$121
-
kW-mo/yr
|
- | - | |
| TOTAL RECOMMENDED | $76,923 | $190,510 |
$47,181
1,401,650
kWh
|
$20,486
-
kW-mo/yr
|
$5,296
-
MMBtu
|
$3,960 | ||
| TOTAL IMPLEMENTED | $62,557 | $188,160 |
$38,531
1,144,677
kWh
|
$14,770
-
kW-mo/yr
|
$5,296
-
MMBtu
|
$3,960 | ||
| Yearly Savings* | Imp'd Cost* | Electricity Usage Savings | Electricity Demand Savings | Natural Gas Savings | Personnel Changes Savings | |||
*Savings and costs are best estimates based on the center's site visit, associated engineering analysis, and typical capital and labor costs