Assessment Year | 2013 |
---|---|
Principal Product | Concrete Railroad Products |
NAICS | 327390: Other Concrete Product Manufacturing |
SIC | 3272: Concrete Products, Except Block and Brick |
Sales Range | $10 M to 50M |
# of Employees | 45 |
Plant Area |
70,000
ft2
|
Annual Production | 22,000
pieces
|
Production Hrs. Annual | 2,500
hrs
|
Location (State) | Ohio |
Facility Energy Cost and Usage
Source | Yearly Cost | Usage | Unit Cost | |
---|---|---|---|---|
Electricity Usage | $38,593 | 588,480 |
kWh
|
$0.066 |
Electricity Demand | $22,238 | 3,936 |
kW-mo/yr
|
$5.65 |
Electricity Fees | $14,040 | - |
|
- |
Natural Gas | $30,433 | 5,469 |
MMBtu
|
$5.56 |
TOTAL YEARLY COSTS | - | |||
RECOMMENDED SAVINGS* | $16,923 |
See individual recommendations below
*Non-energy impacts included in savings.
|
||
IMPLEMENTED SAVINGS* | $6,417 |
Recommendations
# | Description | Yearly Savings* | Imp'd Cost* | Status | Electricity Usage Savings | Electricity Demand Savings | Natural Gas Savings | Personnel Changes Savings |
---|---|---|---|---|---|---|---|---|
01 | 2.4111: Utilize energy-efficient belts and other improved mechanisms | $711 | - |
$389
5,935
kWh
|
$322
-
kW-mo/yr
|
- | - | |
02 | 2.6218: Turn off equipment when not in use | $350 | $250 |
$350
5,334
kWh
|
- | - | - | |
03 | 2.6218: Turn off equipment when not in use | $184 | - |
$121
1,845
kWh
|
$63
-
kW-mo/yr
|
- | - | |
04 | 2.4239: Eliminate or reduce compressed air usage | $5,267 | $4,330 |
$1,885
28,738
kWh
|
$3,382
-
kW-mo/yr
|
- | - | |
05 | 2.4231: Reduce the pressure of compressed air to the minimum required | $26 | - |
$26
395
kWh
|
- | - | - | |
06 | 2.2533: Replace air curtain doors with solid doors | $1,159 | $1,578 |
$(-19.0)
(-297)
kWh
|
- |
$1,178
-
MMBtu
|
- | |
07 | 2.2113: Repair or replace steam traps | $3,389 | $9,600 | - | - |
$3,389
-
MMBtu
|
- | |
08 | 2.1233: Analyze flue gas for proper air/fuel ratio | $1,001 | $500 | - | - |
$1,001
-
MMBtu
|
- | |
09 | 2.7142: Utilize higher efficiency lamps and/or ballasts | $3,862 | $19,001 |
$2,956
45,082
kWh
|
$823
-
kW-mo/yr
|
- | $83 | |
10 | 2.7142: Utilize higher efficiency lamps and/or ballasts | $974 | $10,900 |
$699
10,653
kWh
|
$275
-
kW-mo/yr
|
- | - | |
TOTAL RECOMMENDED | $16,923 | $46,159 |
$6,407
97,685
kWh
|
$4,865
-
kW-mo/yr
|
$5,568
-
MMBtu
|
$83 | ||
TOTAL IMPLEMENTED | $6,417 | $22,078 |
$1,190
18,136
kWh
|
$660
-
kW-mo/yr
|
$4,567
-
MMBtu
|
- | ||
Yearly Savings* | Imp'd Cost* | Electricity Usage Savings | Electricity Demand Savings | Natural Gas Savings | Personnel Changes Savings |
*Savings and costs are best estimates based on the center's site visit, associated engineering analysis, and typical capital and labor costs