ITAC Assessment: MI0046
ITAC logo
ITAC Assessment: MI0046
Grant Funding Opportunity NOW OPEN
Up to $300k at 50% cost share for qualifying* projects.
Grant Funding Opportunity Open
Qualifying* small and medium-sized US manufacturers, that received an ITAC, Onsite Energy/CHP TAP, or qualified equivalent assessment since 2018 can now apply for grants for implementation of assessment recommendations at up to 50% of qualifying* project costs with a maximum of $300,000 per grant.
IMPORTANT: The grant program now operates on a rolling basis and applications may be submitted at any time through the year, with quarterly reviews.
*See Full Grant Solicitation for full qualification and selection details.
Assessment Year 2002
Principal Product Sand and gravel quarry
NAICS
n/a
SIC 1442: Construction Sand and Gravel
Sales Range $10
M
to 50
M
# of Employees 25
Plant Area
n/a
Annual Production 2,000,000
ton
Production Hrs. Annual 2,730
hrs
Location (State) Florida

Facility Energy Cost and Usage

Source Yearly Cost Usage
Electricity Usage $184,929 3,238,237
kWh
Electricity Demand $83,777 29,529
kW-mo/yr
TOTAL YEARLY COSTS -
RECOMMENDED SAVINGS* $134,958 *Non-energy impacts included in savings.
IMPLEMENTED SAVINGS* $60,708

Recommendations

# Description Yearly Savings* Imp'd Cost* Status Electricity Usage Savings Electricity Demand Savings Primary Product Savings
01 4.611: Begin a practice of predictive / preventative maintenance $74,250 $5,460 - - $74,250
02 4.651: Install back-up equipment $27,428 $936 - - $27,428
03 2.3131: Reschedule plant operations or reduce load to avoid peaks $16,162 $1,016 - $16,162
-
kW-mo/yr
-
04 2.4111: Utilize energy-efficient belts and other improved mechanisms $9,120 $1,068 $8,178
136,309
kWh
$942
-
kW-mo/yr
-
05 3.1191: Change procedures / equipment / operating conditions $7,998 $8 - - $7,998
TOTAL RECOMMENDED $134,958 $8,488 $8,178
136,309
kWh
$17,104
-
kW-mo/yr
$109,676
TOTAL IMPLEMENTED $60,708 $3,028 $8,178
136,309
kWh
$17,104
-
kW-mo/yr
$35,426
*Savings and costs are best estimates based on the center's site visit, associated engineering analysis, and typical capital and labor costs