Assessment Year | 2002 |
---|---|
Principal Product | Sand and gravel quarry |
NAICS |
n/a
|
SIC | 1442: Construction Sand and Gravel |
Sales Range | $10 M to 50M |
# of Employees | 25 |
Plant Area |
n/a
|
Annual Production | 2,000,000
ton
|
Production Hrs. Annual | 2,730
hrs
|
Location (State) | Florida |
Facility Energy Cost and Usage
Source | Yearly Cost | Usage | Unit Cost | |
---|---|---|---|---|
Electricity Usage | $184,929 | 3,238,237 |
kWh
|
$0.057 |
Electricity Demand | $83,777 | 29,529 |
kW-mo/yr
|
$2.84 |
TOTAL YEARLY COSTS | - | |||
RECOMMENDED SAVINGS* | $134,958 |
See individual recommendations below
*Non-energy impacts included in savings.
|
||
IMPLEMENTED SAVINGS* | $60,708 |
Recommendations
# | Description | Yearly Savings* | Imp'd Cost* | Status | Electricity Usage Savings | Electricity Demand Savings | Primary Product Savings |
---|---|---|---|---|---|---|---|
01 | 4.611: Begin a practice of predictive / preventative maintenance | $74,250 | $5,460 | - | - | $74,250 | |
02 | 4.651: Install back-up equipment | $27,428 | $936 | - | - | $27,428 | |
03 | 2.3131: Reschedule plant operations or reduce load to avoid peaks | $16,162 | $1,016 | - |
$16,162
-
kW-mo/yr
|
- | |
04 | 2.4111: Utilize energy-efficient belts and other improved mechanisms | $9,120 | $1,068 |
$8,178
136,309
kWh
|
$942
-
kW-mo/yr
|
- | |
05 | 3.1191: Change procedures / equipment / operating conditions | $7,998 | $8 | - | - | $7,998 | |
TOTAL RECOMMENDED | $134,958 | $8,488 |
$8,178
136,309
kWh
|
$17,104
-
kW-mo/yr
|
$109,676 | ||
TOTAL IMPLEMENTED | $60,708 | $3,028 |
$8,178
136,309
kWh
|
$17,104
-
kW-mo/yr
|
$35,426 |
*Savings and costs are best estimates based on the center's site visit, associated engineering analysis, and typical capital and labor costs