| Assessment Year | 2002 |
|---|---|
| Principal Product | Sand and gravel quarry |
| NAICS |
n/a
|
| SIC | 1442: Construction Sand and Gravel |
| Sales Range | $10 M to 50M |
| # of Employees | 25 |
| Plant Area |
n/a
|
| Annual Production | 2,000,000
ton
|
| Production Hrs. Annual | 2,730
hrs
|
| Location (State) | Florida |
Facility Energy Cost and Usage
| Source | Yearly Cost | Usage | Unit Cost | |
|---|---|---|---|---|
| Electricity Usage | $184,929 | 3,238,237 |
kWh
|
$0.057 |
| Electricity Demand | $83,777 | 29,529 |
kW-mo/yr
|
$2.84 |
| TOTAL YEARLY COSTS | - | |||
| RECOMMENDED SAVINGS* | $134,958 |
See individual recommendations below
*Non-energy impacts included in savings.
|
||
| IMPLEMENTED SAVINGS* | $60,708 | |||
Recommendations
| # | Description | Yearly Savings* | Imp'd Cost* | Status | Electricity Usage Savings | Electricity Demand Savings | Primary Product Savings |
|---|---|---|---|---|---|---|---|
| 01 | 4.611: Begin a practice of predictive / preventative maintenance | $74,250 | $5,460 | - | - | $74,250 | |
| 02 | 4.651: Install back-up equipment | $27,428 | $936 | - | - | $27,428 | |
| 03 | 2.3131: Reschedule plant operations or reduce load to avoid peaks | $16,162 | $1,016 | - |
$16,162
-
kW-mo/yr
|
- | |
| 04 | 2.4111: Utilize energy-efficient belts and other improved mechanisms | $9,120 | $1,068 |
$8,178
136,309
kWh
|
$942
-
kW-mo/yr
|
- | |
| 05 | 3.1191: Change procedures / equipment / operating conditions | $7,998 | $8 | - | - | $7,998 | |
| TOTAL RECOMMENDED | $134,958 | $8,488 |
$8,178
136,309
kWh
|
$17,104
-
kW-mo/yr
|
$109,676 | ||
| TOTAL IMPLEMENTED | $60,708 | $3,028 |
$8,178
136,309
kWh
|
$17,104
-
kW-mo/yr
|
$35,426 | ||
*Savings and costs are best estimates based on the center's site visit, associated engineering analysis, and typical capital and labor costs