Assessment Year | 2013 |
---|---|
Principal Product | Defense Combat Vehicles |
NAICS | 336992: Military Armored Vehicle, Tank, and Tank Component Manufacturing |
SIC | 3795: Tanks and Tank Components |
Sales Range | $100 M to 500M |
# of Employees | 550 |
Plant Area |
1,600,000
ft2
|
Annual Production | 150
pieces
|
Production Hrs. Annual | 2,125
hrs
|
Location (State) | Ohio |
Facility Energy Cost and Usage
Source | Yearly Cost | Usage | Unit Cost | |
---|---|---|---|---|
Electricity Usage | $2,061,206 | 46,527,600 |
kWh
|
$0.044 |
Electricity Demand | $1,180,412 | 93,636 |
kW-mo/yr
|
$12.61 |
Natural Gas | $662,576 | 145,461 |
MMBtu
|
$4.56 |
Coal | $1,272,701 | 200,198 |
MMBtu
|
$6.36 |
TOTAL YEARLY COSTS | - | |||
RECOMMENDED SAVINGS* | $2,288,717 |
See individual recommendations below
*Non-energy impacts included in savings.
|
||
IMPLEMENTED SAVINGS* | $767,386 |
Recommendations
# | Description | Yearly Savings* | Imp'd Cost* | Status | Electricity Usage Savings | Natural Gas Savings | Coal Savings | Administrative Changes Savings | One-time Revenue or Avoided Cost Savings |
---|---|---|---|---|---|---|---|---|---|
01 | 2.1331: Burn a less expensive grade of fuel | $544,478 | - |
$33,135
768,082
kWh
|
$(-640,879.0)
-
MMBtu
|
$1,152,222
-
MMBtu
|
- | - | |
02 | 2.1233: Analyze flue gas for proper air/fuel ratio | $1,847 | - | - |
$1,847
-
MMBtu
|
- | - | - | |
03 | 2.8118: Check for accuracy of utility / power meters | $37,340 | - | - | - | - | - | $37,340 | |
04 | 2.7124: Make a practice of turning off lights when not needed | $136,711 | - |
$136,711
3,169,000
kWh
|
- | - | - | - | |
05 | 2.7142: Utilize higher efficiency lamps and/or ballasts | $10,587 | $19,427 |
$10,009
232,016
kWh
|
- | - | $578 | - | |
06 | 2.7124: Make a practice of turning off lights when not needed | $5,216 | - |
$5,216
120,918
kWh
|
- | - | - | - | |
07 | 2.6212: Turn off equipment during breaks, reduce operating time | $37,438 | $6,000 |
$7,844
181,838
kWh
|
$29,594
-
MMBtu
|
- | - | - | |
08 | 2.4111: Utilize energy-efficient belts and other improved mechanisms | $6,203 | - |
$6,203
143,780
kWh
|
- | - | - | - | |
09 | 2.4226: Use / purchase optimum sized compressor | $176,886 | $101,000 |
$176,886
4,100,283
kWh
|
- | - | - | - | |
10 | 2.7224: Reduce space conditioning during non-working hours | $746,973 | $100,000 |
$112,915
2,617,416
kWh
|
$173,812
-
MMBtu
|
$460,246
-
MMBtu
|
- | - | |
11 | 2.7231: Use radiant heater for spot heating | $565,879 | $1,157,500 | - |
$(-452,279.0)
-
MMBtu
|
$1,018,158
-
MMBtu
|
- | - | |
12 | 2.6212: Turn off equipment during breaks, reduce operating time | $19,159 | - |
$19,159
444,119
kWh
|
- | - | - | - | |
TOTAL RECOMMENDED | $2,288,717 | $1,383,927 |
$508,078
11,777,452
kWh
|
$(-887,905.0)
-
MMBtu
|
$2,630,626
-
MMBtu
|
$578 | $37,340 | ||
TOTAL IMPLEMENTED | $767,386 | $6,000 |
$189,109
4,383,618
kWh
|
$(-611,285.0)
-
MMBtu
|
$1,152,222
-
MMBtu
|
- | $37,340 | ||
Yearly Savings* | Imp'd Cost* | Electricity Usage Savings | Natural Gas Savings | Coal Savings | Administrative Changes Savings | One-time Revenue or Avoided Cost Savings |
*Savings and costs are best estimates based on the center's site visit, associated engineering analysis, and typical capital and labor costs