Assessment Year | 2013 |
---|---|
Principal Product | Activated Carbon |
NAICS | 325180: Other Basic Inorganic Chemical Manufacturing |
SIC | 2819: Industrial Inorganic Chemicals, Not Elsewhere Classified |
Sales Range | $10 M to 50M |
# of Employees | 50 |
Plant Area |
181,945
ft2
|
Annual Production | 14,000,000
lb
|
Production Hrs. Annual | 8,760
hrs
|
Location (State) | Ohio |
Facility Energy Cost and Usage
Source | Yearly Cost | Usage | Unit Cost | |
---|---|---|---|---|
Electricity Usage | $236,328 | 3,339,484 |
kWh
|
$0.071 |
Electricity Demand | $45,015 | 7,968 |
kW-mo/yr
|
$5.65 |
Natural Gas | $425,139 | 116,168 |
MMBtu
|
$3.66 |
TOTAL YEARLY COSTS | - | |||
RECOMMENDED SAVINGS* | $109,328 |
See individual recommendations below
*Non-energy impacts included in savings.
|
||
IMPLEMENTED SAVINGS* | $26,284 |
Recommendations
# | Description | Yearly Savings* | Imp'd Cost* | Status | Electricity Usage Savings | Electricity Demand Savings | Natural Gas Savings | Administrative Changes Savings | One-time Revenue or Avoided Cost Savings |
---|---|---|---|---|---|---|---|---|---|
01 | 2.8112: Combine utility meters | $18,015 | $72,060 | - | - | - | - | $18,015 | |
02 | 2.7142: Utilize higher efficiency lamps and/or ballasts | $12,622 | $24,525 |
$11,326
155,639
kWh
|
$640
-
kW-mo/yr
|
- | $656 | - | |
03 | 2.4111: Utilize energy-efficient belts and other improved mechanisms | $2,257 | - |
$2,038
28,039
kWh
|
$219
-
kW-mo/yr
|
- | - | - | |
04 | 2.4151: Develop a repair/replace policy | $1,024 | $1,525 |
$925
12,709
kWh
|
$99
-
kW-mo/yr
|
- | - | - | |
05 | 2.4323: Use optimum size and capacity equipment | $2,823 | $1,200 | - |
$2,823
-
kW-mo/yr
|
- | - | - | |
06 | 2.4239: Eliminate or reduce compressed air usage | $2,640 | $6,800 |
$2,384
32,764
kWh
|
$256
-
kW-mo/yr
|
- | - | - | |
07 | 2.7314: Reduce ventilation air | $1,515 | $3,000 |
$1,368
18,801
kWh
|
$147
-
kW-mo/yr
|
- | - | - | |
08 | 2.4231: Reduce the pressure of compressed air to the minimum required | $1,410 | $50 |
$1,274
17,520
kWh
|
$136
-
kW-mo/yr
|
- | - | - | |
09 | 2.4236: Eliminate leaks in inert gas and compressed air lines/ valves | $371 | $1,000 |
$877
12,046
kWh
|
$94
-
kW-mo/yr
|
- | $(-600.0) | - | |
10 | 2.2414: Use waste heat from hot flue gases to preheat | $3,191 | $15,000 | - | - |
$3,191
-
MMBtu
|
- | - | |
11 | 2.2163: Use minimum steam operating pressure | $184 | $200 | - | - |
$184
-
MMBtu
|
- | - | |
12 | 2.1116: Improve combustion control capability | $133 | $100 | - | - |
$133
-
MMBtu
|
- | - | |
13 | 2.2414: Use waste heat from hot flue gases to preheat | $20,343 | $55,500 | - | - |
$20,343
-
MMBtu
|
- | - | |
14 | 2.2414: Use waste heat from hot flue gases to preheat | $14,378 | $11,500 | - | - |
$14,378
-
MMBtu
|
- | - | |
15 | 2.2514: Cover open tanks | $3,707 | $3,174 | - | - |
$3,707
-
MMBtu
|
- | - | |
16 | 2.3413: Burn fossil fuel to produce steam to drive a steam turbine-generator and use steam exhaust for heat | $24,715 | $101,000 |
$31,873
438,000
kWh
|
$3,420
-
kW-mo/yr
|
$(-6,198.0)
-
MMBtu
|
$(-4,380.0) | - | |
TOTAL RECOMMENDED | $109,328 | $296,634 |
$52,065
715,518
kWh
|
$7,834
-
kW-mo/yr
|
$35,738
-
MMBtu
|
$(-4,324.0) | $18,015 | ||
TOTAL IMPLEMENTED | $26,284 | $49,400 |
$17,947
246,671
kWh
|
$4,173
-
kW-mo/yr
|
$3,508
-
MMBtu
|
$656 | - | ||
Yearly Savings* | Imp'd Cost* | Electricity Usage Savings | Electricity Demand Savings | Natural Gas Savings | Administrative Changes Savings | One-time Revenue or Avoided Cost Savings |
*Savings and costs are best estimates based on the center's site visit, associated engineering analysis, and typical capital and labor costs