Assessment Year | 1995 |
---|---|
Principal Product | Extruded Aluminum |
NAICS |
n/a
|
SIC | 3442: Metal Doors, Sash, Frames, Molding, and Trim Manufacturing |
Sales Range | $10 M to 50M |
# of Employees | 150 |
Plant Area |
380,000
ft2
|
Annual Production | 17,000,000
lb
|
Production Hrs. Annual | 6,864
hrs
|
Location (State) | Georgia |
Facility Energy Cost and Usage
Source | Yearly Cost | Usage | Unit Cost | |
---|---|---|---|---|
Electricity Usage | $645,094 | 10,269,637 |
kWh
|
$0.063 |
TOTAL YEARLY COSTS | - | |||
RECOMMENDED SAVINGS* | $248,123 |
See individual recommendations below
*Non-energy impacts included in savings.
|
||
IMPLEMENTED SAVINGS* | $68,781 |
Recommendations
# | Description | Yearly Savings* | Imp'd Cost* | Status | Electricity Usage Savings | Natural Gas Savings | Other Liquid (haz) Savings | Solid Waste (non-haz) Savings | Administrative Changes Savings | By-product Production Savings |
---|---|---|---|---|---|---|---|---|---|---|
01 | 2.7142: Utilize higher efficiency lamps and/or ballasts | $3,722 | $9,249 |
$3,722
64,771
kWh
|
- | - | - | - | - | |
02 | 2.7142: Utilize higher efficiency lamps and/or ballasts | $14,429 | $23,286 |
$14,429
246,776
kWh
|
- | - | - | - | - | |
03 | 2.7142: Utilize higher efficiency lamps and/or ballasts | $167 | $280 |
$167
2,345
kWh
|
- | - | - | - | - | |
04 | 2.4133: Use most efficient type of electric motors | $5,838 | $15,023 |
$5,838
90,270
kWh
|
- | - | - | - | - | |
05 | 2.4236: Eliminate leaks in inert gas and compressed air lines/ valves | $5,737 | $850 |
$5,737
90,270
kWh
|
- | - | - | - | - | |
06 | 2.2222: Convert liquid heaters from underfiring to immersion or submersion heating | $12,460 | $11,600 | - |
$12,460
-
MMBtu
|
- | - | - | - | |
07 | 2.4146: Use adjustable frequency drive or multiple speed motors on existing system | $17,287 | $35,300 |
$17,287
360,199
kWh
|
- | - | - | - | - | |
08 | 2.7134: Use photocell controls | $2,518 | $400 |
$2,518
43,376
kWh
|
- | - | - | - | - | |
09 | 3.5315: Lease / purchase baler; sell cardboard to recycler | $36,323 | $8,765 | - | - | - |
$36,323
-
lb
|
- | - | |
10 | 3.6112: Use filter and drying oven to reduce sludge volume | $5,121 | $8,000 | - | - |
$5,121
-
gal
|
- | - | - | |
11 | 4.821: Pay bills on time to avoid late fees | $3,769 | - | - | - | - | - | $3,769 | - | |
12 | 3.5248: Separate and recycle scrap metal to foundry or for sale | $140,752 | - | - | - | - | - | - | $140,752 | |
TOTAL RECOMMENDED | $248,123 | $112,753 |
$49,698
898,007
kWh
|
$12,460
-
MMBtu
|
$5,121
-
gal
|
$36,323
-
lb
|
$3,769 | $140,752 | ||
TOTAL IMPLEMENTED | $68,781 | $48,604 |
$28,689
473,037
kWh
|
- | - |
$36,323
-
lb
|
$3,769 | - | ||
Yearly Savings* | Imp'd Cost* | Electricity Usage Savings | Natural Gas Savings | Other Liquid (haz) Savings | Solid Waste (non-haz) Savings | Administrative Changes Savings | By-product Production Savings |
*Savings and costs are best estimates based on the center's site visit, associated engineering analysis, and typical capital and labor costs