Assessment Year | 2012 |
---|---|
Principal Product | castings |
NAICS | 331524: Aluminum Foundries (except Die-Casting) |
SIC | 3365: Aluminum Foundries |
Sales Range | $10 M to 50M |
# of Employees | 180 |
Plant Area |
85,000
ft2
|
Annual Production | 65,000
pieces
|
Production Hrs. Annual | 8,500
hrs
|
Location (State) | Missouri |
Facility Energy Cost and Usage
Source | Yearly Cost | Usage | Unit Cost | |
---|---|---|---|---|
Electricity Usage | $332,034 | 5,004,600 |
kWh
|
$0.066 |
Natural Gas | $130,346 | 16,626 |
MMBtu
|
$7.84 |
TOTAL YEARLY COSTS | - | |||
RECOMMENDED SAVINGS* | $102,203 |
See individual recommendations below
*Non-energy impacts included in savings.
|
||
IMPLEMENTED SAVINGS* | $102,203 |
Recommendations
# | Description | Yearly Savings* | Imp'd Cost* | Status | Electricity Usage Savings | Electricity Demand Savings | Natural Gas Savings |
---|---|---|---|---|---|---|---|
01 | 2.4236: Eliminate leaks in inert gas and compressed air lines/ valves | $16,034 | $860 |
$15,233
230,809
kWh
|
$801
-
kW-mo/yr
|
- | |
02 | 2.2511: Insulate bare equipment | $4,444 | $4,000 | - | - |
$4,444
-
MMBtu
|
|
03 | 2.2511: Insulate bare equipment | $9,628 | $8,667 | - | - |
$9,628
-
MMBtu
|
|
04 | 2.2511: Insulate bare equipment | $11,110 | $9,100 | - | - |
$11,110
-
MMBtu
|
|
05 | 2.3412: Use waste heat to produce steam to drive a steam turbine-generator | $58,850 | $120,000 |
$55,910
847,128
kWh
|
$2,940
-
kW-mo/yr
|
- | |
06 | 2.1233: Analyze flue gas for proper air/fuel ratio | $2,137 | $1,700 | - | - |
$2,137
-
MMBtu
|
|
07 | 4.431: Train operators for maximum operating efficiency | $0.1 | - |
$0.1
1
kWh
|
- | - | |
TOTAL RECOMMENDED | $102,203 | $144,327 |
$71,143
1,077,938
kWh
|
$3,741
-
kW-mo/yr
|
$27,319
-
MMBtu
|
||
TOTAL IMPLEMENTED | $102,203 | $144,327 |
$71,143
1,077,938
kWh
|
$3,741
-
kW-mo/yr
|
$27,319
-
MMBtu
|
||
Yearly Savings* | Imp'd Cost* | Electricity Usage Savings | Electricity Demand Savings | Natural Gas Savings |
*Savings and costs are best estimates based on the center's site visit, associated engineering analysis, and typical capital and labor costs