ITAC Assessment: UD0866
ITAC logo
ITAC Assessment: UD0866
Grant Funding Opportunity NOW OPEN
Up to $300k at 50% cost share for qualifying* projects.
Grant Funding Opportunity Open
Qualifying* small and medium-sized US manufacturers, that received an ITAC, Onsite Energy/CHP TAP, or qualified equivalent assessment since 2018 can now apply for grants for implementation of assessment recommendations at up to 50% of qualifying* project costs with a maximum of $300,000 per grant.
IMPORTANT: The grant program now operates on a rolling basis and applications may be submitted at any time through the year, with quarterly reviews.
*See Full Grant Solicitation for full qualification and selection details.
Assessment Year 2012
Principal Product Packaged bacon - raw and cooked
NAICS 311612: Meat Processed from Carcasses
SIC 2013: Sausages and Other Prepared Meat Products
Sales Range $100
M
to 500
M
# of Employees 424
Plant Area 100,000
ft2
Annual Production 66,000,000
lb
Production Hrs. Annual 5,460
hrs
Location (State) Ohio

Facility Energy Cost and Usage

Source Yearly Cost Usage
Electricity Usage $1,900,842 29,250,841
kWh
Electricity Demand $189,820 66,780
kW-mo/yr
Natural Gas $210,512 32,849
MMBtu
TOTAL YEARLY COSTS -
RECOMMENDED SAVINGS* $230,333 *Non-energy impacts included in savings.
IMPLEMENTED SAVINGS* $154,197

Recommendations

# Description Yearly Savings* Imp'd Cost* Status Electricity Usage Savings Electricity Demand Savings Natural Gas Savings Administrative Changes Savings
01 2.7142: Utilize higher efficiency lamps and/or ballasts $22,071 $41,345 $20,119
317,136
kWh
$1,433
-
kW-mo/yr
- $519
02 2.7142: Utilize higher efficiency lamps and/or ballasts $13,212 $29,160 $11,427
180,121
kWh
$820
-
kW-mo/yr
- $965
03 2.7135: Install occupancy sensors $7,111 $12,160 $5,737
90,434
kWh
$409
-
kW-mo/yr
- $965
04 2.7135: Install occupancy sensors $5,702 $140 $5,320
83,866
kWh
$382
-
kW-mo/yr
- -
05 2.7142: Utilize higher efficiency lamps and/or ballasts $5,120 $10,460 $3,877
61,107
kWh
$278
-
kW-mo/yr
- $965
06 2.4231: Reduce the pressure of compressed air to the minimum required $7,378 $22,134 $6,952
109,580
kWh
$426
-
kW-mo/yr
- -
07 2.4236: Eliminate leaks in inert gas and compressed air lines/ valves $3,740 - $4,089
64,450
kWh
$251
-
kW-mo/yr
- $(-600.0)
08 2.4224: Upgrade controls on compressors $3,050 - $2,716
42,840
kWh
$334
-
kW-mo/yr
- -
09 2.4322: Use or replace with energy efficient substitutes $583 $1,300 $549
8,653
kWh
$34
-
kW-mo/yr
- -
10 2.2163: Use minimum steam operating pressure $83,103 $83,103 $132,265
2,084,880
kWh
$8,111
-
kW-mo/yr
$(-57,273.0)
-
MMBtu
-
11 2.2113: Repair or replace steam traps $28,807 - - - $28,807
-
MMBtu
-
12 2.2414: Use waste heat from hot flue gases to preheat $12,878 $20,000 - - $12,878
-
MMBtu
-
13 2.2163: Use minimum steam operating pressure $10,985 $32,955 - - $10,985
-
MMBtu
-
14 2.1233: Analyze flue gas for proper air/fuel ratio $10,212 $8,000 - - $10,212
-
MMBtu
-
15 2.2136: Install / repair insulation on steam lines $9,098 $10,982 - - $9,098
-
MMBtu
-
16 2.2696: Use excess cold process fluid for industrial cooling needs $7,283 $15,600 $7,283
100,832
kWh
- - -
TOTAL RECOMMENDED $230,333 $287,339 $200,334
3,143,899
kWh
$12,478
-
kW-mo/yr
$14,707
-
MMBtu
$2,814
TOTAL IMPLEMENTED $154,197 $157,564 $163,425
2,576,046
kWh
$10,221
-
kW-mo/yr
$(-19,368.0)
-
MMBtu
$(-81.0)
Yearly Savings* Imp'd Cost* Electricity Usage Savings Electricity Demand Savings Natural Gas Savings Administrative Changes Savings
*Savings and costs are best estimates based on the center's site visit, associated engineering analysis, and typical capital and labor costs