Assessment Year | 2012 |
---|---|
Principal Product | Packaged bacon - raw and cooked |
NAICS | 311612: Meat Processed from Carcasses |
SIC | 2013: Sausages and Other Prepared Meat Products |
Sales Range | $100 M to 500M |
# of Employees | 424 |
Plant Area |
100,000
ft2
|
Annual Production | 66,000,000
lb
|
Production Hrs. Annual | 5,460
hrs
|
Location (State) | Ohio |
Facility Energy Cost and Usage
Source | Yearly Cost | Usage | Unit Cost | |
---|---|---|---|---|
Electricity Usage | $1,900,842 | 29,250,841 |
kWh
|
$0.065 |
Electricity Demand | $189,820 | 66,780 |
kW-mo/yr
|
$2.84 |
Natural Gas | $210,512 | 32,849 |
MMBtu
|
$6.41 |
TOTAL YEARLY COSTS | - | |||
RECOMMENDED SAVINGS* | $230,333 |
See individual recommendations below
*Non-energy impacts included in savings.
|
||
IMPLEMENTED SAVINGS* | $154,197 |
Recommendations
# | Description | Yearly Savings* | Imp'd Cost* | Status | Electricity Usage Savings | Electricity Demand Savings | Natural Gas Savings | Administrative Changes Savings |
---|---|---|---|---|---|---|---|---|
01 | 2.7142: Utilize higher efficiency lamps and/or ballasts | $22,071 | $41,345 |
$20,119
317,136
kWh
|
$1,433
-
kW-mo/yr
|
- | $519 | |
02 | 2.7142: Utilize higher efficiency lamps and/or ballasts | $13,212 | $29,160 |
$11,427
180,121
kWh
|
$820
-
kW-mo/yr
|
- | $965 | |
03 | 2.7135: Install occupancy sensors | $7,111 | $12,160 |
$5,737
90,434
kWh
|
$409
-
kW-mo/yr
|
- | $965 | |
04 | 2.7135: Install occupancy sensors | $5,702 | $140 |
$5,320
83,866
kWh
|
$382
-
kW-mo/yr
|
- | - | |
05 | 2.7142: Utilize higher efficiency lamps and/or ballasts | $5,120 | $10,460 |
$3,877
61,107
kWh
|
$278
-
kW-mo/yr
|
- | $965 | |
06 | 2.4231: Reduce the pressure of compressed air to the minimum required | $7,378 | $22,134 |
$6,952
109,580
kWh
|
$426
-
kW-mo/yr
|
- | - | |
07 | 2.4236: Eliminate leaks in inert gas and compressed air lines/ valves | $3,740 | - |
$4,089
64,450
kWh
|
$251
-
kW-mo/yr
|
- | $(-600.0) | |
08 | 2.4224: Upgrade controls on compressors | $3,050 | - |
$2,716
42,840
kWh
|
$334
-
kW-mo/yr
|
- | - | |
09 | 2.4322: Use or replace with energy efficient substitutes | $583 | $1,300 |
$549
8,653
kWh
|
$34
-
kW-mo/yr
|
- | - | |
10 | 2.2163: Use minimum steam operating pressure | $83,103 | $83,103 |
$132,265
2,084,880
kWh
|
$8,111
-
kW-mo/yr
|
$(-57,273.0)
-
MMBtu
|
- | |
11 | 2.2113: Repair or replace steam traps | $28,807 | - | - | - |
$28,807
-
MMBtu
|
- | |
12 | 2.2414: Use waste heat from hot flue gases to preheat | $12,878 | $20,000 | - | - |
$12,878
-
MMBtu
|
- | |
13 | 2.2163: Use minimum steam operating pressure | $10,985 | $32,955 | - | - |
$10,985
-
MMBtu
|
- | |
14 | 2.1233: Analyze flue gas for proper air/fuel ratio | $10,212 | $8,000 | - | - |
$10,212
-
MMBtu
|
- | |
15 | 2.2136: Install / repair insulation on steam lines | $9,098 | $10,982 | - | - |
$9,098
-
MMBtu
|
- | |
16 | 2.2696: Use excess cold process fluid for industrial cooling needs | $7,283 | $15,600 |
$7,283
100,832
kWh
|
- | - | - | |
TOTAL RECOMMENDED | $230,333 | $287,339 |
$200,334
3,143,899
kWh
|
$12,478
-
kW-mo/yr
|
$14,707
-
MMBtu
|
$2,814 | ||
TOTAL IMPLEMENTED | $154,197 | $157,564 |
$163,425
2,576,046
kWh
|
$10,221
-
kW-mo/yr
|
$(-19,368.0)
-
MMBtu
|
$(-81.0) | ||
Yearly Savings* | Imp'd Cost* | Electricity Usage Savings | Electricity Demand Savings | Natural Gas Savings | Administrative Changes Savings |
*Savings and costs are best estimates based on the center's site visit, associated engineering analysis, and typical capital and labor costs