ITAC Assessment: UD0865
ITAC logo
ITAC Assessment: UD0865
Grant Funding Opportunity NOW OPEN
Up to $300k at 50% cost share for qualifying* projects.
Grant Funding Opportunity Open
Qualifying* small and medium-sized US manufacturers, that received an ITAC, Onsite Energy/CHP TAP, or qualified equivalent assessment since 2018 can now apply for grants for implementation of assessment recommendations at up to 50% of qualifying* project costs with a maximum of $300,000 per grant.
IMPORTANT: The grant program now operates on a rolling basis and applications may be submitted at any time through the year, with quarterly reviews.
*See Full Grant Solicitation for full qualification and selection details.
Assessment Year 2012
Principal Product beer
NAICS 312120: Breweries
SIC 2082: Malt Beverages
Sales Range $100
M
to 500
M
# of Employees 110
Plant Area 125,000
ft2
Annual Production 572,333
units
Production Hrs. Annual 8,400
hrs
Location (State) Ohio

Facility Energy Cost and Usage

Source Yearly Cost Usage
Electricity Usage $567,967 9,244,344
kWh
Electricity Demand $115,892 21,732
kW-mo/yr
Natural Gas $496,353 103,893
MMBtu
TOTAL YEARLY COSTS -
RECOMMENDED SAVINGS* $156,883 *Non-energy impacts included in savings.
IMPLEMENTED SAVINGS* -

Recommendations

# Description Yearly Savings* Imp'd Cost* Status Electricity Usage Savings Electricity Demand Savings Electricity Fees Savings Natural Gas Savings
01 2.3212: Optimize plant power factor $3,291 $8,000 - - $3,291 -
02 2.7135: Install occupancy sensors $4,289 $1,200 $3,728
62,133
kWh
$561
-
kW-mo/yr
- -
03 2.4133: Use most efficient type of electric motors $30,494 $36,750 $23,578
392,964
kWh
$6,916
-
kW-mo/yr
- -
04 2.4236: Eliminate leaks in inert gas and compressed air lines/ valves $1,395 $1,000 $1,035
27,243
kWh
$360
-
kW-mo/yr
- -
05 2.4226: Use / purchase optimum sized compressor $1,071 $1,500 $1,071
17,857
kWh
- - -
06 2.4221: Install compressor air intakes in coolest locations $992 $1,000 $813
13,550
kWh
$179
-
kW-mo/yr
- -
07 2.4226: Use / purchase optimum sized compressor $966 $1,600 $792
13,200
kWh
$174
-
kW-mo/yr
- -
08 2.1233: Analyze flue gas for proper air/fuel ratio $5,463 - - - - $5,463
-
MMBtu
09 2.1113: Reduce combustion air flow to optimum $4,015 $9,000 - - - $4,015
-
MMBtu
10 2.2692: Use outside cold water source as a supply of cooling water $3,073 $9,219 $2,471
41,186
kWh
$602
-
kW-mo/yr
- -
11 2.2437: Recover waste heat from equipment $42,877 $83,500 $6,714
107,792
kWh
- - $36,163
-
MMBtu
12 2.2628: Utilize a less expensive cooling method $20,832 $25,000 $19,279
321,322
kWh
$1,553
-
kW-mo/yr
- -
13 2.2628: Utilize a less expensive cooling method $15,846 $24,600 $15,846
264,098
kWh
- - -
14 2.2626: Avoid frost formation on evaporators $7,322 - $7,322
122,040
kWh
- - -
15 2.3413: Burn fossil fuel to produce steam to drive a steam turbine-generator and use steam exhaust for heat $14,957 $123,000 $18,000
300,000
kWh
$3,960
-
kW-mo/yr
- $(-7,003.0)
-
MMBtu
TOTAL RECOMMENDED $156,883 $325,369 $100,649
1,683,385
kWh
$14,305
-
kW-mo/yr
$3,291 $38,638
-
MMBtu
TOTAL IMPLEMENTED - - - - - -
Yearly Savings* Imp'd Cost* Electricity Usage Savings Electricity Demand Savings Electricity Fees Savings Natural Gas Savings
*Savings and costs are best estimates based on the center's site visit, associated engineering analysis, and typical capital and labor costs