Assessment Year | 2012 |
---|---|
Principal Product | Infrared Cameras |
NAICS | 334220: Radio and Television Broadcasting and Wireless Communications Equipment Manufacturing |
SIC | 3663: Radio and Television Broadcasting and Communications Equipment |
Sales Range | $100 M to 500M |
# of Employees | 550 |
Plant Area |
243,000
ft2
|
Annual Production | 10,000
pieces
|
Production Hrs. Annual | 3,672
hrs
|
Location (State) | Ohio |
Facility Energy Cost and Usage
Source | Yearly Cost | Usage | Unit Cost | |
---|---|---|---|---|
Electricity Usage | $791,758 | 15,963,603 |
kWh
|
$0.050 |
Electricity Demand | $383,503 | 32,196 |
kW-mo/yr
|
$11.91 |
Natural Gas | $237,070 | 41,347 |
MMBtu
|
$5.73 |
TOTAL YEARLY COSTS | - | |||
RECOMMENDED SAVINGS* | $243,998 |
See individual recommendations below
*Non-energy impacts included in savings.
|
||
IMPLEMENTED SAVINGS* | $20,166 |
Recommendations
# | Description | Yearly Savings* | Imp'd Cost* | Status | Electricity Usage Savings | Electricity Demand Savings | Natural Gas Savings |
---|---|---|---|---|---|---|---|
01 | 2.4146: Use adjustable frequency drive or multiple speed motors on existing system | $6,307 | $2,925 |
$3,413
75,169
kWh
|
$2,894
-
kW-mo/yr
|
- | |
02 | 2.4146: Use adjustable frequency drive or multiple speed motors on existing system | $6,307 | $2,925 |
$3,413
75,169
kWh
|
$2,894
-
kW-mo/yr
|
- | |
03 | 2.4146: Use adjustable frequency drive or multiple speed motors on existing system | $2,365 | $2,650 |
$1,280
28,188
kWh
|
$1,085
-
kW-mo/yr
|
- | |
04 | 2.4146: Use adjustable frequency drive or multiple speed motors on existing system | $2,365 | $2,650 |
$1,280
28,188
kWh
|
$1,085
-
kW-mo/yr
|
- | |
05 | 2.4224: Upgrade controls on compressors | $5,184 | - |
$5,184
114,176
kWh
|
- | - | |
06 | 2.4221: Install compressor air intakes in coolest locations | $888 | $1,300 |
$655
14,420
kWh
|
$233
-
kW-mo/yr
|
- | |
07 | 2.6218: Turn off equipment when not in use | $1,934 | - |
$1,934
42,593
kWh
|
- | - | |
08 | 2.7233: Use properly designed and sized hvac equipment | $191,536 | $383,074 |
$66,738
1,470,000
kWh
|
$23,721
-
kW-mo/yr
|
$101,077
-
MMBtu
|
|
09 | 2.2622: Replace existing chiller with high efficiency model | $27,112 | $122,500 |
$20,044
441,504
kWh
|
$7,068
-
kW-mo/yr
|
- | |
TOTAL RECOMMENDED | $243,998 | $518,024 |
$103,941
2,289,407
kWh
|
$38,980
-
kW-mo/yr
|
$101,077
-
MMBtu
|
||
TOTAL IMPLEMENTED | $20,166 | $12,450 |
$11,975
263,727
kWh
|
$8,191
-
kW-mo/yr
|
- | ||
Yearly Savings* | Imp'd Cost* | Electricity Usage Savings | Electricity Demand Savings | Natural Gas Savings |
*Savings and costs are best estimates based on the center's site visit, associated engineering analysis, and typical capital and labor costs