Assessment Year | 2012 |
---|---|
Principal Product | rubber vibration isolation |
NAICS | 326291: Rubber Product Manufacturing for Mechanical Use |
SIC | 3061: Molded, Extruded, and Lathe-Cut Mechanical Rubber Goods |
Sales Range | $100 M to 500M |
# of Employees | 450 |
Plant Area |
205,000
ft2
|
Annual Production | 100,000,000
pieces
|
Production Hrs. Annual | 8,400
hrs
|
Location (State) | Ohio |
Facility Energy Cost and Usage
Source | Yearly Cost | Usage | Unit Cost | |
---|---|---|---|---|
Electricity Usage | $1,135,919 | 17,246,230 |
kWh
|
$0.066 |
Electricity Demand | $194,051 | 36,069 |
kW-mo/yr
|
$5.38 |
Natural Gas | $337,193 | 68,728 |
MMBtu
|
$4.91 |
TOTAL YEARLY COSTS | - | |||
RECOMMENDED SAVINGS* | $199,430 |
See individual recommendations below
*Non-energy impacts included in savings.
|
||
IMPLEMENTED SAVINGS* | $99,893 |
Recommendations
# | Description | Yearly Savings* | Imp'd Cost* | Status | Electricity Usage Savings | Electricity Demand Savings | Electricity Fees Savings | Natural Gas Savings | Water Disposal Savings | Administrative Changes Savings |
---|---|---|---|---|---|---|---|---|---|---|
01 | 3.4113: Treat and reuse rinse waters | $23,578 | $1,000 | - | - | - | - |
$23,578
-
Tgal
|
- | |
02 | 2.8112: Combine utility meters | $4,421 | $8,842 | - | - | $4,421 | - | - | - | |
03 | 2.7142: Utilize higher efficiency lamps and/or ballasts | $7,407 | $16,259 |
$6,288
98,784
kWh
|
$886
-
kW-mo/yr
|
- | - | - | $233 | |
04 | 2.4111: Utilize energy-efficient belts and other improved mechanisms | $557 | - |
$488
7,682
kWh
|
$69
-
kW-mo/yr
|
- | - | - | - | |
05 | 2.4133: Use most efficient type of electric motors | $16,871 | $8,000 |
$15,053
236,496
kWh
|
$1,818
-
kW-mo/yr
|
- | - | - | - | |
06 | 2.4239: Eliminate or reduce compressed air usage | $18,285 | $9,900 |
$16,315
256,331
kWh
|
$1,970
-
kW-mo/yr
|
- | - | - | - | |
07 | 2.4239: Eliminate or reduce compressed air usage | $16,249 | - |
$14,498
227,784
kWh
|
$1,751
-
kW-mo/yr
|
- | - | - | - | |
08 | 2.4221: Install compressor air intakes in coolest locations | $8,548 | $2,000 |
$7,626
119,809
kWh
|
$922
-
kW-mo/yr
|
- | - | - | - | |
09 | 2.4236: Eliminate leaks in inert gas and compressed air lines/ valves | $8,856 | $1,000 |
$7,902
124,148
kWh
|
$954
-
kW-mo/yr
|
- | - | - | - | |
10 | 2.2113: Repair or replace steam traps | $13,284 | - | - | - | - |
$13,284
-
MMBtu
|
- | - | |
11 | 2.2113: Repair or replace steam traps | $10,008 | $2,600 | - | - | - |
$10,008
-
MMBtu
|
- | - | |
12 | 2.1241: Reduce excessive boiler blowdown | $4,619 | $12,800 | - | - | - |
$4,619
-
MMBtu
|
- | - | |
13 | 2.7221: Lower temperature during the winter season and vice-versa | $43,532 | - | - | - | - |
$43,532
-
MMBtu
|
- | - | |
14 | 2.6231: Utilize controls to operate equipment only when needed | $23,215 | $14,000 | - | - | - |
$23,215
-
MMBtu
|
- | - | |
TOTAL RECOMMENDED | $199,430 | $76,401 |
$68,170
1,071,034
kWh
|
$8,370
-
kW-mo/yr
|
$4,421 |
$94,658
-
MMBtu
|
$23,578
-
Tgal
|
$233 | ||
TOTAL IMPLEMENTED | $99,893 | $19,859 |
$29,176
458,398
kWh
|
$3,660
-
kW-mo/yr
|
- |
$66,824
-
MMBtu
|
- | $233 | ||
Yearly Savings* | Imp'd Cost* | Electricity Usage Savings | Electricity Demand Savings | Electricity Fees Savings | Natural Gas Savings | Water Disposal Savings | Administrative Changes Savings |
*Savings and costs are best estimates based on the center's site visit, associated engineering analysis, and typical capital and labor costs